Additional Binding Offtakes and Financing Update
Released
Released
Announcement PDF
ASX Announcement
11 December 2025
Additional Binding Offtakes and Financing Update
for Arrowsmith North
Highlights:
Two additional binding offtake contracts signed
Offtake customers are well-established, reputable
and substantial suppliers into foundry and
glassmaking industries in China
Adds 550,000 tonnes of offtake commitments for
Arrowsmith North silica sand for an aggregate of
960,000 tonnes per year
Pareto Securities appointed to manage Arrowsmith
North fixed income financing
VRX Silica Limited (ASX:VRX) (VRX or Company) is pleased
to announce that it has secured additional binding offtake
contracts for its Arrowsmith North Silica Sand Project
(Arrowsmith North) and appointed an international bank to
manage financing.
Offtake
The two new offtake contracts are for the supply of an
aggregate minimum of 550,000 tonnes per annum of high-
quality silica sand products from Arrowsmith North to two well-
established, reputable and substantial suppliers into the
foundry and glassmaking industries in China.
These additional contracts follow VRX’s announcement to ASX
in October1 of four binding contracts for the supply of a minimum
of 410,000 tonnes of silica sand products from Arrowsmith
North, equating to an aggregate 960,000 tonnes committed
under contract.
It follows continued testing of samples of silica sand products
from Arrowsmith North confirming that these would be sought-
after products. In particular, the key features for preferred
foundry sand are particle size distribution, grain shape and size
and thermal stability, which all are attributes of Arrowsmith
North silica sand to demonstrate its superior quality and ability
to meet the highest stringent specifications.
1 ASX announcement “Binding Offtake Contracts Secured for Arrowsmith North” dated 23 October 2025
ASX: VRX
Capital Structure
Shares:
778.3 million
Options:
43.7 million
Corporate Directory
Paul Boyatzis
Non-Executive Chairman
Bruce Maluish
Managing Director
Peter Pawlowitsch
Non-Executive Director
David Welch
Non-Executive Director
Ian Hobson
Company Secretary
Silica Sand Projects
Arrowsmith Silica Sand
Projects, 270km north of
Perth, WA.
Muchea Silica Sand
Project, 50km north of
Perth, WA.
Boyatup Silica Sand
Project, 100km east of
Esperance, WA.
The Company is actively
assessing other silica sand
and downstream
processing projects in
Australia.
2
VRX Managing Director Bruce Maluish said: “These additional binding offtake contracts further
demonstrate substantial interest in VRX’s Arrowsmith North silica sand foundry and
glassmaking products. These offtake partners are well established companies in their industry
and we expect them to be long term buyers as we diversify our customer base.
“These contracts vindicate VRX’s strategy to ensure production of a unique Australian and
highly sought-after product, and to secure the right customers for our silica sand products.
“They also provide confidence to VRX with regards to sales and revenue generation and form
an important precondition for potential debt financiers.”
Arrowsmith North, 270km north of Perth, contains a globally significant deposit of high-quality
silica sand underpinning a mining project that will enable long term production for the foundry,
container glass and flat-glass markets in Asia. As detailed in the updated bankable feasibility
study announced in March 2024, Arrowsmith North has a JORC-compliant Proved and
Probable Ore Reserve of 221Mt @ 99.5% SiO2.2
The contracts set out detailed terms and conditions for the supply by Ventnor Mining Pty Ltd,
a 100% owned subsidiary of VRX and owner of the Arrowsmith North mining tenements,
shipped FOB from the Port of Geraldton, of an aggregate minimum 550,000 tonnes per annum
of Midwest premium glassmaking sand and AFS20, 35 & 55 certified foundry sand for a period
of four years, with pricing fixed for the first two years within the range of the Company’s
financial modelling for Arrowsmith North as provided in the March 2024 updated bankable
feasibility study.
Key assumptions for the updated bankable feasibility study include a target price range of
US$38-43 per dry metric tonne, dependent on product type, product quality, contract terms
and quantity, and a targeted production schedule of up to 2.2 million tonnes per annum over
the full mine life with a conservative ramp up from a minimum 800,000 tonnes to 1.1 million
tonnes per annum in years 1 and 2.
Each contract is subject to customary conditions precedent relating to commencement of the
project, including the Company finalising project finance, receiving all remaining permits for
the project, finalising logistics contracts for transport and port access and usage,
commissioning of Arrowsmith North and its related infrastructure to achieve commercial
production, and delivery of an initial trial shipment. The conditions must be satisfied by
31 December 2026 with a right for the Company to extend this date by up to four months.
The contracts are on terms and conditions that are customary for agreements of this nature
and are in line with industry standard documentation including provisions around contract
performance, delivery of product, quality control, weighing and sampling, shipping and laycan,
force majeure, termination rights and the application of Incoterms® 2020 rules.
VRX considers that disclosing the specific identities of the counterparties to the offtake
contracts is not information a reasonable person would expect to have a material effect on the
price or value of its securities, given the counterparties’ standing and creditworthiness. VRX
confirms that this announcement includes all material information relevant to assessing the
impact of these offtake agreements on the price or value of the Company’s securities and is
not misleading by omission.
With several binding offtake contracts now in place, the Company has sufficient sales of silica
sand products committed for its initial production schedule and to move forward with financing.
2 See the updated bankable feasibility study released to ASX in 2024 (ASX announcement “Arrowsmith North Updated BFS”
dated 6 March 2024)
3
Debt Financing
VRX has appointed international investment bank and debt capital markets specialist Pareto
Securities (Pareto) as Manager for fixed income debt financing to support the construction of
the Arrowsmith North project.
The appointment follows a competitive process and reflects the strong interest in Arrowsmith
North.
VRX looks forward to working with Pareto and its financial adviser, Argonaut, to progress the
debt financing over the coming months.
This announcement has been authorised for release to ASX by VRX Managing Director, Bruce
Maluish.
Further information:
Bruce Maluish Peter Klinger
Managing Director Purple
brucem@vrxsilica.com.au pklinger@purple.au
4
About VRX’s target silica sand markets
Foundry
Silica sand is an essential part of both the ferrous and non-ferrous foundry industries. Metal
parts ranging from engine blocks to sink faucets are cast in a sand-and-clay mould to produce
their external shape, often using a resin coat to create the desired internal shape. Silica’s high
fusion point (1,760°C) and low rate of thermal expansion produce stable cores and moulds
compatible with all pouring temperatures. Its chemical purity also helps prevent interaction
with catalysts or affecting the curing rate of chemical binders, for that reason, customers are
looking for high quality silica sand that meets their specifications for size and shape.
Another critical specification is the hardness of silica grains to deliver the required crush
resistance to high pressure from molten metals.
Arrowsmith North is capable of producing multiple high quality sand products for the foundry
industry as confirmed by potential offtake partners in Asia following extensive testwork.
Glassmaking
Silica sand is the primary component of all types of standard and specialty glass. It provides
the essential SiO2 component of glass formulation and its chemical purity is the primary
determinant of colour, clarity and strength in glass. Silica sand is used to produce flat glass
for building and automotive use, container glass for foods and beverages, and tableware. In
its pulverised form, ground silica is required in the production of fibreglass insulation and for
reinforcing glass fibres. Specialty glass applications include test tubes and other scientific
tools, incandescent and fluorescent lamps, television and computer LCD/LED monitors.
Glassmaking physical specifications focus on particle size, as it significantly impacts melting
efficiency. Uniform grain size is preferred to reduce energy use and ensure complete melting.
In fibreglass production, over 99.5% of raw material grains are smaller than 0.045 mm (45μm),
and tighter limits are being considered. Coarse particles are hardest to melt and can cause
defects. Grain shape also matters—if too many grains are coarser than specified, incomplete
melting and poor product quality can result.
Refractory heavy minerals (RHM)—such as iron, zircon, corundum, chrome spinels, rutile,
and staurolite—should generally be avoided in glassmaking because they do not melt at
standard glass-making temperatures. This leads to solid inclusions or defects ("stones") in
the final glass. Limits on RHM are typically based on their size and amount, with particles
larger than 0.25 mm (10 mesh) being the most problematic. These may be restricted by
weight percentage or particle count.
5
About VRX Silica Limited
VRX Silica Limited (ASX: VRX) is the most advanced pureplay silica sand company listed on the
ASX, developing its 100% owned silica sand projects at Arrowsmith (North, Brand and Central),
Muchea and Boyatup in Western Australia.
Silica sand is the most used commodity on
the planet after air and water. It is the main
ingredient in all types of glassmaking,
including specialty solar panel and high-
tech glass, and foundry casting. It is a
finite resource that is running out, with the
Asia-Pacific region experiencing an ever-
growing supply shortfall that is driving up
prices.
Arrowsmith is located 270km north of
Perth. Arrowsmith North boasts a minimum
25-year mine life capable of producing
more than 2Mt tonnes per year of high-
grade (99.7% SiO2)* silica sand for export
to the foundry, container glass and flat
glass markets in Asia, with permitting well
advanced, and will lead production.
Muchea, located 50km north of Perth, is an
ultra-high-grade (99.9% SiO2)* silica sand
project capable of producing sand required
for ultra-clear glass for solar panels and
other high-tech glass applications.
Boyatup, located 100km east of Esperance,
is under
development and capable of producing
sand for the glass market.
*Information relating to grades are extracted from releases to ASX on 28 August 2019 and 11 November 2022
(Arrowsmith North) and 18 October 2019 (Muchea). The company is not aware of any new information or data that
materially affects this information.
6
Appendix
Arrowsmith North Ore Reserves and Grades
Project Classification Product Mt
SiO2
%
Al2O3
%
Fe2O3
%
TiO2
%
LOI
%
Arrowsmith
North
Proved
AFS20 0.8 99.5 0.25 0.07 0.05 0.1
AFS35 3.9 99.5 0.5 0.06 0.05 0.1
AFS55 2.7 99.2 0.5 0.1 0.05 0.1
Local 1.8
Proved Ore Reserve 9.2 Million Tonnes
Probable
AFS20 24.2 99.5 0.25 0.07 0.05 0.1
AFS35 102.5 99.5 0.5 0.06 0.05 0.1
AFS55 51.1 99.2 0.5 0.1 0.05 0.1
Local 34.1
Probable Ore Reserve 212 Million Tonnes
Total Ore Reserves 221 Million Tonnes
Compliance Statement – Ore Reserves and Grades
The information in this document that relates to the estimation and reporting of the Ore
Reserves for the Arrowsmith North silica sand project is extracted from releases to ASX on 28
August 2019, 11 November 2022 and 6 March 2024. The Company confirms that it is not
aware of any new information or data that materially affects the information included in this
document and all material assumptions and technical parameters underpinning the estimates
in those releases continue to apply and have not materially changed.
Compliance Statement – Production Target
The information in this document that relates to the Company’s production target for the
Arrowsmith North silica sand project is extracted from releases to ASX on 6 March 2024. The
Company confirms that it is not aware of any new information or data that materially affects the
information included in this document and all material assumptions underpinning the
production target continue to apply and have not materially changed.
The Company also confirms that the form and context in which the Competent Person’s
findings are presented have not been materially modified from the relevant original market
announcements.