Engineering Completed on Arrowsmith North Processing Plant
Released
Released
Announcement PDF
ASX Announcement
29 May 2023
VRX COMPLETES ENGINEERING ON ARROWSMITH
NORTH PROCESSING PLANT
Highlights:
Detailed engineering complete
Mechanical equipment list finalised
Supply tender documents prepared
Critical timelines established.
ASX: VRX
Capital Structure
Shares on Issue:
560.4 million
Unlisted Options:
41.3 million
Corporate Directory
VRX Silica Limited (ASX: VRX) (VRX or Company) is pleased
to announce that it has completed all material engineering work
for construction of a 2 million tonne per year silica sand
processing plant at its Arrowsmith North Silica Sand Project,
270km north of Perth.
The detailed design phase of the project is largely complete.
Remaining minor areas/items will be easily and efficiently detail
designed during the execution phase of the project, without
affecting the execution schedule.
This phase of engineering has been based on a
comprehensive metallurgical testwork program and peer
reviewed process circuit design and testing.
The design incorporates some innovative processing
techniques which allows flexibility for the Company to produce
multiple products subject to market requirements for foundry
and glassmaking silica sand.
VRX Managing Director Bruce Maluish said: “This stage of the
project follows an extensive testing program that VRX has
conducted over the last few years.
“The Company has developed with its metallurgical consultants
a number of unique processes to produce the most valuable,
high yield and high-quality silica sand products possible.
“This design work by the engineering team at ProjX, will allow
a very long production regime at Arrowsmith North with low
emissions and carbon footprint.”
Paul Boyatzis
Non-Executive Chairman
Bruce Maluish
Managing Director
Peter Pawlowitsch
Non-Executive Director
David Welch
Non-Executive Director
Ian Hobson
Company Secretary
Silica Sand Projects
Arrowsmith Silica Sand
Projects, 270km north of
Perth, WA.
Muchea Silica Sand
Project, 50km north of
Perth, WA.
Boyatup Silica Sand
Project, 100km east of
Esperance, WA.
The Company is actively
assessing other silica
sand projects in
Australia.
DETAILED DESIGN
The following areas/items are detail designed, peer reviewed and ready to progress to
execution:
•
Site and plant layout drawings.
•
The attritioning/flotation building (structural, mechanical, and concrete packages).
•
The product area (structural, mechanical, and concrete packages).
•
Rejects cyclone stacker.
•
Civil works for the plant & product area.
•
Civil works for the southern access road.
•
Civil works for the Brand Highway interface. (Note that this has been fully approved by
Main Roads WA).
•
Concrete has been detail designed.
•
Electrical reticulation design and single line diagrams.
•
Process Flow Diagrams (PFDs).
•
Piping & Instrumentation Diagrams (PIDs).
•
Circuit mass balance.
•
Water management
•
Mechanical Equipment List (MEL).
•
Fabrication drawings verified.
•
3D design model.
The functional control philosophy document is currently being developed.
The following areas/items are concept designed only and will be detail designed or completed
during the execution phase of the project:
•
The mine plant area, including the feed hopper, transfer conveyors, trommel and other
associated equipment such as water tank & pump skids, pipe systems etc. This area
is all concept designed but is essentially comprised of vendor equipment linked
together. The trommel is sourced and refurbished, and the other vendor equipment
has been tendered and the preferred vendor selected. Finalisation of this area and
design of ancillary items will be completed during the execution phase.
•
Non-Process Infrastructure (NPI) will be designed/selected during the execution phase
but have been included in site layout drawings. This includes items such as the
following:
o
Admin, crib, toilet buildings etc and associated water and wastewater system.
o
Fire and raw water services.
o
Workshop, stores, laydown, etc.
o
Vehicle wash bays.
2
EQUIPMENT
The following major equipment has been tendered, selected as preferred and therefore used
in the detailed design:
•
Cyclone cluster
•
Attritioners
•
Hydrofloat separators
•
Classifiers
•
Conditioning tank
•
Thickener
•
Transformers
•
Ring main unit
•
MCC/switchrooms
•
Product dewatering screens
•
Feed hopper and conveyors (preferred vendor yet to be selected)
•
Slurry pumps (preferred vendor yet to be selected)
•
Water pumps
•
Air compressors
The following minor equipment is yet to be officially tendered:
•
Bore pumpset.
•
Transportable buildings.
•
Samplers.
•
Pipe supply.
•
Fabricated steelwork, chutes, etc.
Several items of secondhand process equipment have been purchased and refurbished:
•
A second hand feed trommel was purchased, refurbished, and is now in storage in a
Bunbury fabrication contractor’s premises. This machine is the primary screening
machine at the mine plant.
•
A vibrating screen (Schenck vibrating banana screen) was purchased, refurbished,
and is now in storage at a Bunbury workshop. This machine is the final product sizing
screen.
3
Feed Trommel
Schenk vibrating banana screen
4
PROJECT EXECUTION SCHEDULE
The most recent execution schedule uses the following key milestones prior to the decision to
commence construction:
•
Finalise finance and establish commencement date.
•
Site access date to construct the northern access road.
•
Approval to place orders for major long lead equipment.
•
Site access date for plant construction.
PROJECT COST ESTIMATE
The baseline project cost estimate, determined at a preliminary level in 2019, was $28.3M
(including ~$6M contingency). The cost estimate will be updated during 2023 as key
equipment has been re-tendered. The cost estimate will be refined and updated prior to the
decision to commence construction.
MAJOR EQUIPMENT PROCUREMENT
VRX has prepared a summary of the major long lead time equipment that will be procured and
has recently refreshed the quotations for most of these items. Some equipment has not been
retendered for some time and will require retendering closer to the execution phase. Timing
for procurement is subject to the EPA approvals process.
When evaluating tenders VRX uses a Tender Evaluation (TEV) process to summarise the
tender submissions and to essentially land on the preferred tender.
SHORT TERM ONGOING WORKS
VRX intends to carry on with the following development tasks.
•
Rearrange the execution cost estimate to show costs by area rather than by task, for
inclusion in the data room for DD by financiers. This is a short-term priority.
•
Evaluate recent retendering of key major equipment and follow up on other equipment
that has not been retendered recently.
•
Continuously update a summary of lead times for major equipment suppliers to carry
out the detailed design of their equipment, in order to reduce their equipment lead
times.
•
Continue to refine the execution cost estimate in light of recent retendered equipment
and other information.
•
Refine the execution schedule estimate in light of recent retendered equipment and
other information.
•
Produce a manning histogram for the execution phase and investigate accommodation
planning as necessary.
•
Review the Operating & Control Philosophy.
•
Liaise with the power provider to assist with the development of the preferred power
option
5
About VRX Silica Limited
VRX Silica Limited (ASX: VRX) is the most
advanced pureplay silica sand company listed on the
ASX, developing its 100% owned silica sand projects
at Arrowsmith (North, Brand and Central), Muchea
and Boyatup in Western Australia.
Silica sand is the most used commodity on the planet
after air and water. It is the main ingredient in all
types of glassmaking, including specialty solar panel
and high-tech glass, and foundry casting. It is a finite
resource that is running out, with the Asia-Pacific
region experiencing an ever-growing supply shortfall
that is driving up prices.
Arrowsmith is located 270km north of Perth.
Arrowsmith North boasts a minimum 25-year mine
life capable of producing more than 2Mt tonnes per
year of high-grade (99.7% SiO2)* silica sand for
export to the foundry, container glass and flat glass
markets in Asia, with permitting well advanced, and
will lead production.
Muchea, located 50km north of Perth, is an ultrahigh-grade (99.9% SiO2)* silica sand project capable
of producing sand required for ultra-clear glass for
solar panels and other high-tech glass applications.
Boyatup, located 100km east of Esperance, is under
development and capable of producing sand for the glass market.
*Information relating to grades are extracted from releases to ASX on 28 August 2019 and 11 November 2022
(Arrowsmith North) and 18 October 2019 (Muchea). The company is not aware of any new information or data that
materially affects this information.