Arrowsmith Central Water Bore
6 September 2022
ASX ANNOUNCEMENT
Arrowsmith Central – Water Bore
Highlights:
Test holes completed for shallow and deep
aquifers
Production bore drilling underway
Pump testing to follow for abstraction licence
application
VRX Silica Limited (VRX or the Company) (ASX: VRX) is
pleased to provide an update on progress at its 100%-owned
Arrowsmith Central Silica Sand Project (Arrowsmith Central),
located approximately 270km north of Perth, Western Australia.
ASX: VRX
Capital Structure
Shares on Issue:
558.4 million
Unlisted Options:
35.3 million
Corporate Directory
The Company has completed the test holes for 2 production
water bores which will be the source of water supply for the
proposed processing plant at Arrowsmith Central. The test
holes are targeting 2 potential aquifers at 30 metre and 120
metre depth. Geological and geophysical logging of the holes
indicate good potential for high flows of good quality ground
water. Neither aquifer is believed to be connected to the
superficial water table.
Paul Boyatzis
Non-Executive Chairman
Bruce Maluish
Managing Director
Peter Pawlowitsch
Non-Executive Director
David Welch
Non-Executive Director
Ian Hobson
Company Secretary
VRX Managing Director Bruce Maluish said:
Silica Sand Projects
“The supply of good quality processing water is a critical step in
the development of the Arrowsmith Central Silica Sand Project.
Arrowsmith Silica Sand
Projects, 270km north of
Perth, WA.
Two potential aquifers are being tested and it is interpreted they
are part of the plentiful Yarragadee North aquifer and therefore
will not affect the superficial aquifer and any groundwater
dependant ecosystems.”
Drilling is being undertaken by a licenced water bore driller, see
Figure 2, under an approved Licence to Construct or Alter a
Well, CAW207418(1), from the Department of Water and
Environmental Regulation (DWER).
DWER has accepted the Company’s application for an
allocation of 900,000 kilolitres. The 5C licence to take water will
be applied for once the bores are constructed, see Figure 3, and
logging and test pumping is complete.
Muchea Silica Sand
Project, 50km north of
Perth, WA.
Boyatup Silica Sand
Project, 100km east of
Esperance, WA.
The Company is actively
assessing other silica
sand projects in
Australia.
The location of the water bore is shown in Figure 1.
Figure 1: Water Bore Location
Figure 2: Water Bore Rig onsite
Figure 3: Deep Production Water Bore Design
This announcement has been authorised for release to ASX by the Managing Director, Bruce
Maluish.
Further information:
Bruce Maluish
Managing Director
brucem@vrxsilica.com.au
0418 940 417
Peter Klinger
Cannings Purple
pklinger@canningspurple.com.au
0411 251 540
About VRX Silica
VRX Silica Ltd (ASX: VRX) is developing a portfolio of world-class, high-grade silica sand projects in Western
Australia.
The Arrowsmith North and Arrowsmith Central Silica Sand Projects, 270km north of Perth, comprise five granted
exploration licences and two granted mining leases. Bankable feasibility studies for both projects have demonstrated
exceptional financial metrics.
The Muchea Silica Sand Project, 50km north of Perth, comprises two granted and one under-application exploration
licences as well as one granted and one under application mining leases. Muchea is a world-class project with highpurity silica sand in situ. A bankable feasibility study has demonstrated outstanding financial metrics.
The Boyatup Silica Sand Project, 100km east of Esperance, comprises two adjacent granted exploration licences.
Indications from a recent drill program and Mineral Resource Estimate indicate that this project can complement the
Arrowsmith and Muchea projects and add to VRX’s range of potential silica products.
Proven Management
VRX Silica’s Board and Leadership Team have extensive experience in mineral exploration and mine developmentto-production and in the management of publicly listed mining and exploration companies.
Silica Sand Projects Locations
Share your feedback
Discover