Update on Arrowsmith North Environmental Approvals Process
ASX Announcement
31 October 2023
Update on Arrowsmith North
Environmental Approvals Process
Highlights:
PER period closed and public submissions
summarised by EPA
VRX draft response to public submissions
lodged with EPA
Important next step progressing environmental
approval for Arrowsmith North
VRX Silica Limited (VRX or Company) (ASX: VRX) is
pleased to provide an update on its application for
environmental approval at its Arrowsmith North Silica Sand
Project (Proposal) located 270km north of Perth, Western
Australia.
On 9 June 2023 the Company announced to ASX that the
Environmental Review Document (ERD) for the Proposal had
been accepted by the Department of Water and
Environmental Regulation (DWER) for publication and a fourweek Public Environmental Review (PER).
The PER period closed on 16 July 2023.
On 7 September 2023 DWER provided the Company with a
summary of the public submissions received during that
period.
In a significant step forward, the Company has now lodged its
response to those public submissions for consideration by the
Environmental Protection Authority of Western Australia
(EPA).
The EPA will now consider those responses and, subject to
further consultation with the Company, will prepare an
assessment report for the Western Australian Environment
Minister in respect of the Proposal.
Environmental approval for Arrowsmith North is crucial and
linked to VRX’s ability to secure other necessary approvals
for mining. This is yet another a significant step in Arrowsmith
North’s approvals process.
ASX: VRX
Capital Structure
Shares on Issue:
583 million
Unlisted Options:
59 million
Corporate Directory
Paul Boyatzis
Non-Executive Chairman
Bruce Maluish
Managing Director
Peter Pawlowitsch
Non-Executive Director
David Welch
Non-Executive Director
Ian Hobson
Company Secretary
Silica Sand Projects
Arrowsmith Silica Sand
Projects, 270km north of
Perth, WA.
Muchea Silica Sand
Project, 50km north of
Perth, WA.
Boyatup Silica Sand
Project, 100km east of
Esperance, WA.
Geothermal Energy
Dandaragan Geothermal
Energy Permit, 145km
north of Perth, WA
The Company is actively
assessing other silica sand
projects in Australia.
VRX Managing Director Bruce Maluish said: “We are pleased to have progressed to the next
stage of the environmental approvals process for Arrowsmith North and appreciate the public
interest in the proposal. The submissions received during the public review period were
reflective of that interest.
“The proposal has the potential to underpin a project lasting many decades and underscores
the enormous economic contribution that could flow to the Irwin Shire in particular and Western
Australia more broadly.
“We again thank shareholders for their continued patience as we have worked on securing the
key approvals for Arrowsmith North.”
Background to the Proposal and Environmental Approvals Process
The Proposal includes the sequential block mining of silica sand, development of a mine feed
plant, moveable surface conveyor, pipeline, processing plant, stockpiles, freshwater supply
bore, access corridor, laydown, administration, water storage and associated infrastructure
including a gas fired power station, communications equipment, offices, a workshop and
additional laydown areas. Access to the site will be via an access road connecting the mine
to Brand Highway. A freshwater supply bore, water pipeline and access road will be located
within the Access Development Envelope (ADE). All other infrastructure will be located within
the Mine Development Envelope (MDE).
The Proposal will result in clearing and rehabilitation of up to 353.8 ha of native vegetation,
14.5 ha of which will remain cleared for the life of the Proposal, and up to 339.3 ha of native
vegetation that will be progressively rehabilitated via Vegetation Direct Transfer (VDT). The
VDT methodology can be viewed at
https://vrxsilica.com.au/miningandrehabilitationmethodology/.
This process includes salvaging and translocating intact sods comprised of soil, sub soil and
vegetation (mulched to a height) to already mined areas for planting. This approach results in
minimal disturbance to plant roots and rapid recovery of native flora.
VRX has previously received confirmation from the Commonwealth Department of Climate
Change, Energy, the Environment and Water for an accredited assessment under the
Environment Protection and Biodiversity Conservation Act 1999 (Cth) (EPBC Act). Accredited
assessment means the Commonwealth can rely on environmental assessments undertaken by
the EPA for the purpose of its approval decisions under the EPBC Act on proposals that may
have a significant impact on a matter of national environmental significance.
VRX has conducted extensive environmental studies on its silica sand projects over a number
of seasons since 2017 in anticipation of requirements of the State and Commonwealth
environmental regulation authorities to undertake approvals assessments. These surveys
commenced shortly after the tenements were acquired and the number and extent of these
surveys have expanded following further consultation with these authorities. The Company has
initially concentrated on gaining approval for development of Arrowsmith North.
The Proposal was referred to the EPA for assessment under Part IV, Section 38 of the
Environmental Protection Act 1986 (WA) (EP Act) in March 2021. The referral was reviewed
and in May 2021 the EPA determined that the Proposal would be assessed. The EPA set the
level of assessment for the Proposal at ‘Public Environmental Review’ or PER, with a
requirement for a proponent-prepared Environmental Scoping Document (ESD) and a fourweek public review period for the ERD.
2
The Company submitted its ESD to the EPA for assessment in September 2021. The ESD was
approved in March 2022.
In May 2022 VRX lodged with the EPA the first-draft ERD for the Proposal. The ERD is a
document required under the PER process. The ERD was prepared according to the EPA’s
Administrative Procedures Manual and other guidance documents and amendments. The ERD
is a comprehensive summary of the Proposal’s environmental setting, the physical elements of
the proposed mine and infrastructure, operational elements, the extent of impacts on the
environment and the proposed rehabilitation and closure plan. VRX received a request from
DWER for further information in early July 2022 and submitted its response later that month.
In November 2022, DWER requested additional information. The Company lodged a revised
ERD and response table in December 2022. VRX then received a request for further
information in April 2023 and provided a final ERD to DWER in May 2023, which was accepted
by DWER on 8 June 2023.
The final ERD, which comprises 341 pages and 32 appendices detailing a comprehensive
environmental impact assessment of the Proposal, was published by the EPA for a four-week
PER period, commencing on 19 June 2023.
Following completion of the four-week PER period DWER compiled public submissions for the
Company to review and these were provided to the Company on 7 September 2023. The
Company has today lodged its response to those public submissions for consideration by the
EPA.
Upon acceptance and publication of the response to submissions, the EPA will prepare an
assessment report that will include recommendations to the Western Australian Environment
Minister on whether to approve the Proposal. If successful, the Minister will sign off on a
Ministerial Statement that will serve as approval for the Proposal.
This announcement has been authorised for release to ASX by the Managing Director, Bruce
Maluish.
Further information:
Bruce Maluish
Managing Director
brucem@vrxsilica.com.au
0418 940 417
Peter Klinger
Cannings Purple
pklinger@canningspurple.com.au
0411 251 540
3
ASX Announcement
About VRX Silica Limited
VRX Silica Limited (ASX: VRX) is the most advanced pureplay silica sand company listed on the
ASX, developing its 100% owned silica sand projects at Arrowsmith (North, Brand and Central),
Muchea and Boyatup in Western Australia.
Silica sand is the most used commodity
on the planet after air and water. It is
the main ingredient in all types of
glassmaking, including specialty solar
panel and high-tech glass, and foundry
casting. It is a finite resource that is
running out, with the Asia-Pacific
region experiencing an ever-growing
supply shortfall that is driving up prices.
Arrowsmith is located 270km north of
Perth. Arrowsmith North boasts a
minimum 25-year mine life capable of
producing more than 2Mt tonnes per
year of high-grade (99.7% SiO2)* silica
sand for export to the foundry,
container glass and flat glass markets
in Asia, with permitting well advanced,
and will lead production.
Muchea, located 50km north of Perth,
is an ultra-high-grade (99.9% SiO2)*
silica sand project capable of producing
sand required for ultra-clear glass for
solar panels and other high-tech glass
applications.
Boyatup, located 100km east of
Esperance, is under
development and capable of producing
sand for the glass market.
*Information relating to grades are extracted from releases to ASX on 28 August 2019 and 11 November 2022
(Arrowsmith North) and 18 October 2019 (Muchea). The company is not aware of any new information or data that
materially affects this information.
Share your feedback