Update on Arrowsmith North Water Bore
Released
Released
Announcement PDF
29 March 2022
ASX ANNOUNCEMENT
Update on Arrowsmith North Water Bore
Highlights:
•
Successful construction and testing of water
production bore at Arrowsmith North
ASX: VRX
•
Confirms reliable supply of water to Arrowsmith North
within specification
Shares on Issue:
558.4 million
Unlisted Options:
35.3 million
VRX Silica Limited (VRX or Company) is pleased to announce
that the Company has successfully completed the construction
and testing of its production water bore at its Arrowsmith North
Silica Sand Project (Arrowsmith North).
As part of the application for a 5C Licence to Take Water a test
production bore and two monitoring bores, a deep and a
shallow, have been drilled and constructed on the Arrowsmith
North miscellaneous licence L70/199 by Western Drilling. The
bores have been constructed to specifications exceeding the
Minimal Construction Requirements for Water Bores in Australia
and as specified by the Department of Water and Environmental
Regulation.
The test production bore is screened in the confined Yarragadee
Formation Unit A aquifer with the screens installed between
320m and 392m depth. The 250mm FRP casing has been
cement grouted from 0 – 300m to prevent ingress of water from
other parts of the Yarragadee Formation or the superficial
aquifer.
Capital Structure
Corporate Directory
Paul Boyatzis
Non-Executive Chairman
Bruce Maluish
Managing Director
Peter Pawlowitsch
Non-Executive Director
David Welch
Non-Executive Director
Ian Hobson
Company Secretary
Silica Sand Projects
Arrowsmith Silica Sand
Projects, 270km north of
Perth, WA.
The deep monitoring bore has a similar construction to the test
production bore with the grouting and screening over similar
intervals. The shallow monitoring bore is screened from 18 –
30m in the superficial aquifer.
Muchea Silica Sand
Project, 50km north of
Perth, WA.
The test production bore was test pumped to determine
hydraulic parameters and specific yields for use in the H3
Hydrogeological Assessment computer model.
Boyatup Silica Sand
Project, 100km east of
Esperance, WA.
The test pumping was undertaken to AS2368-1990 by Western
Irrigation using their mobile test pumping equipment.
The Company is actively
assessing other silica
sand projects in
Australia.
Initial multi-rate testing was carried out to determine a constant
rate test rate. The highest rate of 32L/s yielded a maximum
drawdown of 6.12m.
The constant rate test was carried out at 30L/s for 1,990 minutes for a maximum drawdown of
6.20m in the pumping bore, 2.71m in the deep observation bore and no movement in the
shallow observation bore.
Preliminary assessment of the constant rate test data indicates a transmissivity in excess of
900m3/d/m which results in a hydraulic conductivity in excess of 10m/d.
The controlled test pumping indicates that the confined Yarragadee Formation Unit A aquifer
is capable of yielding the project requirements of 900,000kL per annum. The test production
bore has been constructed to yield in the order of 1,200,000kl per annum.
Analysis of water samples taken during test pumping has confirmed the water is of acceptable
quality for use as process water in VRX’s proposed silica sand process plant.
VRX’s Managing Director Bruce Maluish said: “This is yet another significant step in the
development of the Arrowsmith North Silica Sand Project.
“The production of high quality silica sand requires a reliable water supply and this bore more
than meets our specification. Adequate testing has been completed to allow for VRX to apply
for an abstraction licence from the Dongara basin deep Yarragadee formation without affecting
other users of the superficial water sources.
“Based on the indicative timetable now available to the Company, VRX expects to begin
Arrowsmith North’s six-month construction period in January 2023.”
Test pump
This announcement has been authorised for release to the ASX by VRX Managing Director
Bruce Maluish.
Further information:
Bruce Maluish
Managing Director
brucem@vrxsilica.com.au
0418 940 417
Peter Klinger
Cannings Purple
pklinger@canningspurple.com.au
0411 251 540
About VRX Silica
VRX Silica Ltd (ASX: VRX) is developing world-class, high-grade silica sand projects in Western Australia.
The Arrowsmith North and Arrowsmith Central Silica Sand Projects, 270km north of Perth, comprise two granted
mining leases. Arrowsmith North is at an advanced stage with an EPA approved Environmental Scoping Document.
Bankable feasibility studies for both projects have demonstrated exceptional financial metrics.
The Muchea Silica Sand Project, 50km north of Perth, comprises three granted exploration licences as well as one
granted mining lease. Muchea is a world-class project with high-purity silica sand in situ suitable for beneficiation to
ultra-clear glassmaking quality particularly for solar panels. A bankable feasibility study has demonstrated
outstanding financial metrics.
The Boyatup Silica Sand Project, 100km east of Esperance, comprises two adjacent granted exploration licences.
Initial indications are that this project can complement the Arrowsmith and Muchea projects and add to the range of
silica products VRX Silica may be capable of producing. Drilling is now underway.