Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
June 2023 Quarterly Activity Report
The following is a summary of the activities conducted by VRX Silica Limited (VRX or
Company) during the June 2023 quarter at its silica sand projects at Arrowsmith North,
Arrowsmith Central, Arrowsmith Brand (located 270 km north of Perth), Muchea (located 50
km from Perth) and Boyatup (located 100 km east of Esperance), all situated in Western
Australia.
VRX Silica Sand Resources
VRX is a Western Australian based pure-play silica sand exploration and development
company with five high-value, advanced, very long-term silica sand projects in Western
Australia, a Tier 1 mining region.
The Company has multi-decade scale contiguous sand deposits on granted Mining Leases
with secure tenure and a combined +1.4Bn tonne Mineral Resource11 of 99.6% to 99.9% SiO2
grade silica sand.
The Company and its management team is based in Western Australia, as are its five large
scale, high-grade and low impurity silica sand projects. Each project can be run independently
and supply high-grade silica sand to many diverse markets.
Figure 1: VRX Projects Locations
1 See table on page 8
Applications of Silica Sand
Silica sand is the most-used commodity on the planet after air and water. It is the main
ingredient in all types of glassmaking, including specialty solar panel and high-tech glass.
The glass manufacturing industry demand is increasing at a rate of 5-6% per year, or about
8-10 million tonnes pa. Around 47% of the world’s glass is manufactured in Asia.
Silica sand is an essential component of the foundry and casting industries. The largest
foundry industry is in Korea where it dominates the industry particularly for large marine
components.
Silica sand is also the main ingredient in concrete.
Silica sand is a finite resource that is rapidly being exhausted and the Asia-Pacific region is
currently experiencing increasing demand at a time of a global supply shortfall.
Major Advance In Arrowsmith North Environmental Approvals Process
In June 2023 VRX announced that the Environmental Review Document (ERD) for Arrowsmith
North had been accepted by the Department of Water and Environmental Regulation (DWER)
for publication and a four-week Public Environmental Review (PER).
The PER process commenced on 19 June 2023 for a four week period and included a
requirement for VRX to respond to all comments received. This PER and response process
are the final steps before the Environmental Protection Authority of Western Australia (EPA)
prepares an assessment report including recommendations to the Western Australian
Environment Minister on whether the proposal should be approved.
Environmental approval for Arrowsmith North is crucial and linked to VRX’s ability to secure
other necessary approvals for mining. The PER milestone therefore is a significant step in
Arrowsmith North’s approvals process.
VRX has proposed a unique method for rehabilitation of the mined area that provides for the
best possible outcome for regeneration of native vegetation.
The ERD seeks approval for a development area that has the potential to underpin a project
lasting up to 30 years, underscoring the enormous economic contribution that could flow to the
Irwin Shire in particular and Western Australia more broadly.
VRX has previously received confirmation from the Commonwealth Department of Climate
Change, Energy, the Environment and Water for an accredited assessment under the
Environment Protection and Biodiversity Conservation Act 1999 (Cth) (EPBC Act). Accredited
assessment means the Commonwealth can rely on environmental assessments undertaken by
the EPA for the purpose of its approval decisions under the EPBC Act on proposals that may
have a significant impact on a matter of national environmental significance.
VRX has conducted extensive environmental studies on its silica sand projects over a number
of seasons since 2017 in anticipation of requirements of the State and Commonwealth
environmental regulatory authorities to undertake approvals assessments. These surveys
commenced shortly after the tenements were acquired and the number and extent of these
surveys have expanded following further consultation with these authorities. The Company has
initially concentrated on gaining approval for development of Arrowsmith North.
The Arrowsmith North proposal was referred to the EPA for assessment under Part IV, Section
38 of the Environmental Protection Act 1986 (WA) (EP Act) in March 2021. The referral was
reviewed and in May 2021 the EPA determined that the Proposal would be assessed at a
‘Public Environmental Review’ or PER level, with a requirement for a four-week public review
period.
The Company submitted an Environmental Scoping Document (ESD) to the EPA for
assessment in September 2021. The ESD was approved in March 2022.
2
In May 2022 VRX lodged with the EPA the first-draft ERD for the proposal. The ERD is a
document required under the PER process. The ERD was prepared according to the EPA’s
Administrative Procedures Manual and other guidance documents and amendments. The ERD
is a comprehensive summary of the proposal’s environmental setting, the physical elements of
the proposed mine and infrastructure, operational elements, the extent of impacts on the
environment and the proposed rehabilitation and closure plan. VRX received a number of
requests for further information and provided a final ERD to DWER in May 2023, which was
accepted by DWER on 8 June 2023.
The final ERD, which comprises a 341 page summary and 32 appendices detailing a
comprehensive environmental impact description of the proposal, was published by the EPA
for a four-week PER period, commencing on 19 June 2023.
An important feature of the proposal is the implementation of progressive rehabilitation using
the unique Vegetation Direct Transfer (VDT) method, which is estimated to result in the best
restoration of the vegetation and habitats within the mine area.
The VDT methodology can be viewed at:
https://vrxsilica.com.au/miningandrehabilitationmethodology/
Following completion of the four-week PER period, DWER will compile public submissions for
the Company to review. The Company will then prepare a response to public submissions for
consideration by the EPA.
Importantly this stage of the environmental approvals process for Arrowsmith North will
establish the credentials for the use of VDT in Kwongan Heath, which is the vegetation
encountered at Arrowsmith North and also for the grasses and sedges within Banksia
Woodland at our other projects.
The ERD and further information on the proposal is available on the EPA website at:
https://www.epa.wa.gov.au/proposals/arrowsmith-north-silica-sand-project
A copy of the ERD is also available on the VRX website at:
https://vrxsilica.com.au/arrowsmith-north-erd-documents/
Arrowsmith Brand Mineral Resource Estimate
In May 2023, VRX announced an extension of its known JORC 2012 compliant Resources at
Arrowsmith area with a new Resource at its new Arrowsmith Brand Silica Sand Project, located
270km north of Perth.
The new Resource is contiguous and south of Arrowsmith North and bounded to the south by
the Brand Highway road reserve.
The combined Resources at Arrowsmith now provide a future pipeline of additional production
utilising some of the infrastructure to be developed at Arrowsmith North.
Whilst development of Arrowsmith Brand is not a current priority, extended timelines are now
commonplace for mining approvals and this project has the potential to expand production to
meet ever increasing demand for silica sand products.
The silica sand at Arrowsmith Brand is similar to Arrowsmith North, with testwork to-date from
samples within this Resource has indicated similar products can be produced. Following the
production of the preliminary estimate at Arrowsmith Brand, VRX has lodged an application for
a Mining Lease.
The Arrowsmith Brand Mining Lease Application M 70/1418 has an area of 1,994 Ha and
predominately within Exploration Licence E70/5027, partially within E70/5109 and is contiguous
with the granted Arrowsmith North Mining Lease M70/1389, Figure 2 below. The Mining Lease
was granted subsequent to the end of the quarter on 18 July 2023.
3
Figure 2: Arrowsmith Brand Silica Sand Project Location
4
Detailed Information
An opportunity to generate an additional silica sand project focused on an area of the
Arrowsmith North mineral resource area that is not in the near-term development pipeline. By
splitting Arrowsmith North at the southern boundary of the granted mining lease M70/1389,
see Figure 2, Arrowsmith Brand was established.
Arrowsmith Brand contains a subset of the previously reported Arrowsmith North mineral
resource estimate (MRE)2, also Figure 2. Table 1 shows the prior Arrowsmith North MRE split
between the new Arrowsmith Brand and the Arrowsmith North.
Arrowsmith North - Mineral Resource
11 November 2022 Estimate
Classification
Mt
SiO₂
%
Al₂O₃
%
Fe₂O₃
%
TiO₂
%
LOI
%
Measured
10
95.9
1.9
0.7
0.3
0.7
Indicated
237
97.7
1.00
0.40
0.20
0.50
Inferred
521
98.2
0.80
0.30
0.20
0.40
Total
768
98.0
0.90
0.30
0.20
0.40
Arrowsmith North Mineral Resource
in Arrowsmith Brand Project
Classification
Mt
SiO₂
%
Al₂O₃
%
Fe₂O₃
%
TiO₂
%
LOI
%
Inferred
255
98.0
0.91
0.31
0.17
0.44
Total
255
98.0
0.91
0.31
0.17
0.44
Arrowsmith North Mineral Resource
Ex Arrowsmith Brand Project
Classification
Mt
SiO₂
%
Al₂O₃
%
Fe₂O₃
%
TiO₂
%
LOI
%
Measured
10
95.9
1.9
0.7
0.3
0.7
Indicated
237
97.7
1.0
0.4
0.2
0.5
Inferred
266
98.4
0.7
0.3
0.2
0.4
Total
513
98.0
0.9
0.3
0.2
0.4
Table 1: Prior Arrowsmith North MRE apportioned to Brand Mineral Resource
In December 2022, VRX completed a vacuum drilling program at Arrowsmith North extending
into Arrowsmith Brand, see Figure 3. A total of 68 holes for 786m were drilled on M70/1389 to
gain material for future metallurgical testwork within the proposed Arrowsmith North mining
area. These holes infill the existing 50m spaced grade control drilling which was used to
2 ASX announcement 11 November 2022, “Arrowsmith North Mineral Resource and Ore Reserve Update”.
5
estimate the measured resource and proven reserve1. These samples will not materially
change these estimates and have not been assayed.
An additional 49 holes for 656m were drilled on existing tracks to the south in what is now
known as the Arrowsmith Brand Project. These holes infill and extend the prior reported MRE
for Arrowsmith North. Drilling intersected high quality silica sand which has been assayed and
modelled and has resulted in a MRE for Arrowsmith Brand.
Figure 3 – December 2022 Drill hole locations.
The Arrowsmith Brand MRE is reported in accordance with the JORC Code 2012 Edition.
Drilling was completed generally on an 800m x 800m drill hole grid and defines a band of
6
homogeneous yellow sand overlying white sand. Drilling encountered zones of clay rich fine
sand which was excluded from the MRE. The potential silica sand products from Arrowsmith
Brand are expected to be suitable for industries such as flat, automobile and container glass
manufacturing and foundry casting.
The Arrowsmith Brand MRE is shown in Table 2.
Arrowsmith Brand Mineral Resource Estimate – as at 09/05/2023
Zone
Mt
SiO₂ %
Al₂O₃ %
Fe₂O₃
%
TiO₂ %
LOI %
White
144
98.4
0.8
0.2
0.2
0.4
Yellow
379
96.9
1.6
0.5
0.2
0.7
Total
523
97.3
1.4
0.4
0.2
0.6
Increase over Prior Estimate
268
Classification
Inferred
Million Tonnes
*Note: Interpreted mineralisation is above a basal layer of clay and/or limestone. Depletion zones include the upper 0.3
m excluded for rehabilitation purposes. Only areas with a minimum sand depth of 1m were included. Differences may
occur due to rounding. Prior estimate is summarised in Table 1.
Table 2:
Arrowsmith Brand Mineral Resource
Future Work
In August 2022, VRX lodged a mining lease application over 1,995 Ha, details Table 3 see
Figure 2. The mining lease was granted on 18 July 2023. VRX expects to advance the project
using the well-known process that has been followed at its other silica sand projects currently
being developed. These activities include: environmental surveys, further metallurgical
testwork, marketing studies and mine planning studies, which will inform scoping and prefeasibility studies.
Tenement
Holder
Application date
Grant Date
Area (Ha)
M 70/1418
Ventnor Mining Pty Ltd
01/08/2022
18/07/2023
1,994
Table 3: Arrowsmith Brand tenement details
7
VRX Silica Limited – Summary of Silica Sand Mineral Resources and Ore
Reserves
Mineral Resources - as at 09/05/2023
Project
Muchea
Arrowsmith
North
Arrowsmith
Brand
Arrowsmith
Central
Mt
SiO₂
%
Al₂O₃
%
Fe₂O₃
%
TiO₂
%
LOI
%
Indicated
29
99.6
0.1
0.0
0.1
0.2
Inferred
179
99.6
0.1
0.0
0.1
0.2
Total
208
99.6
0.1
0.0
0.1
0.2
Measured
10
95.9
1.9
0.7
0.3
0.7
Indicated
237
97.7
1.0
0.4
0.2
0.5
Inferred
266
98.4
0.7
0.3
0.2
0.4
Total
513
98.0
0.9
0.3
0.2
0.4
Inferred
523
97.3
1.4
0.4
0.2
0.6
Total
523
97.3
1.4
0.4
0.2
0.6
Indicated
28.2
96.6
1.7
0.4
0.2
0.7
Inferred
48.3
96.9
1.5
0.4
0.2
0.7
Total
76.5
96.8
1.5
0.4
0.2
0.7
Inferred
60
67.8
0.8
0.2
0.1
0.9
Total
60
67.8
0.8
0.2
0.1
0.9
Classification
Boyatup
Table 4: Total Mineral Resource
1,381
Million Tonnes
8
Ore Reserves
Project
SiO2
%
Al2O3
%
Fe2O3
%
TiO2
%
LOI
%
99.9
0.02
0.008
0.03
0.1
4.25
99.8
0.07
0.015
0.035
0.1
18.7
Million Tonnes
AFS20
0.8
99.5
0.25
0.07
0.05
0.1
AFS35
3.9
99.5
0.5
0.06
0.05
0.1
AFS55
2.7
99.2
0.5
0.1
0.05
0.1
Local
1.8
Proved Ore Reserve
9.2
Million Tonnes
AFS20
24.2
99.5
0.25
0.07
0.05
0.1
AFS35
102.5
99.5
0.5
0.06
0.05
0.1
AFS55
51.1
99.2
0.5
0.1
0.05
0.1
Local
34.1
Probable Ore Reserve
212
Million Tonnes
221
Million Tonnes
0.04
0.03
0.1
<1%
2%
Classification
Muchea
Product
Mt
F80
10.2
F80C
4.25
F150
Probable
Muchea Ore Reserve
Proved
Arrowsmith
North
Probable
Arrowsmith North Ore Reserve
Arrowsmith
Central
Probable
CF400
4.2
C20
8.4
C40
4.2
High TiO2
2.2
Arrowsmith Central Ore Reserve
Table 5: Total Ore Reserve
99.6
0.25
18.9
Million Tonnes
259
Million Tonnes
9
VRX Completes Engineering on Arrowsmith North Processing Plant
In May 2023 VRX announced it has completed all material engineering work for construction of
a 2 million tonne per year silica sand processing plant at Arrowsmith North.
The detailed design phase of the project is largely complete. Remaining minor areas/items will
be easily and efficiently detail designed during the execution phase of the project, without
affecting the execution schedule.
This phase of engineering has been based on a comprehensive metallurgical testwork program
and peer reviewed process circuit design and testing.
The design incorporates some innovative processing techniques which allows flexibility for the
Company to produce multiple products subject to market requirements for foundry and
glassmaking silica sand.
This stage of the project follows an extensive testing program that VRX has conducted over the
last few years with its metallurgical consultants. The Company has developed a number of
unique processes to produce the most valuable, high yield and high-quality silica sand products
possible.
This design work by the engineering team at ProjX, will allow a very long production future at
Arrowsmith North with low emissions and carbon footprint.
Detailed Design
The following areas/items are detail designed, peer reviewed and ready to progress to
execution:
•
Site and plant layout drawings.
•
The attritioning/flotation building (structural, mechanical, and concrete packages).
•
The product area (structural, mechanical, and concrete packages).
•
Rejects cyclone stacker.
•
Civil works for the plant & product area.
•
Civil works for the southern access road.
•
Civil works for the Brand Highway interface. (Note that this has been fully approved by
Main Roads WA).
•
Concrete has been detail designed.
•
Electrical reticulation design and single line diagrams.
•
Process Flow Diagrams (PFDs).
•
Piping & Instrumentation Diagrams (PIDs).
•
Circuit mass balance.
•
Water management
•
Mechanical Equipment List (MEL).
•
Fabrication drawings verified.
•
3D design model.
The functional control philosophy document is currently being developed.
10
The following areas/items are concept designed only and will be detail designed or completed
during the execution phase of the project:
•
The mine plant area, including the feed hopper, transfer conveyors, trommel and other
associated equipment such as water tank & pump skids, pipe systems etc. This area
is all concept designed but is essentially comprised of vendor equipment linked
together. The trommel is sourced and refurbished, and the other vendor equipment
has been tendered and the preferred vendor selected. Finalisation of this area and
design of ancillary items will be completed during the execution phase.
•
Non-Process Infrastructure (NPI) will be designed/selected during the execution phase
but have been included in site layout drawings. This includes items such as the
following:
o
Admin, crib, toilet buildings etc and associated water and wastewater system.
o
Fire and raw water services.
o
Workshop, stores, laydown, etc.
o
Vehicle wash bays.
Equipment
The following major equipment has been tendered, selected as preferred and therefore used
in the detailed design:
•
Cyclone cluster
•
Attritioners
•
Hydrofloat separators
•
Classifiers
•
Conditioning tank
•
Thickener
•
Transformers
•
Ring main unit
•
MCC/switchrooms
•
Product dewatering screens
•
Feed hopper and conveyors (preferred vendor yet to be selected)
•
Slurry pumps (preferred vendor yet to be selected)
•
Water pumps
•
Air compressors
The following minor equipment is yet to be officially tendered:
•
Bore pumpset.
•
Transportable buildings.
•
Samplers.
•
Pipe supply.
•
Fabricated steelwork, chutes, etc.
11
Several items of secondhand process equipment have been purchased and refurbished:
•
A second hand feed trommel was purchased, refurbished, and is now in storage in a
Bunbury fabrication contractor’s premises. This machine is the primary screening
machine at the mine plant.
•
A vibrating screen (Schenck vibrating banana screen) was purchased, refurbished,
and is now in storage at a Bunbury workshop. This machine is the final product sizing
screen.
Project Execution Schedule
The most recent execution schedule uses the following key milestones prior to the decision to
commence construction:
•
Finalise finance and establish commencement date.
•
Site access date to construct the northern access road.
•
Approval to place orders for major long lead equipment.
•
Site access date for plant construction.
Project Cost Estimate
The baseline project cost estimate, determined at a preliminary level in 2019, was $28.3M
(including ~$6M contingency). The cost estimate will be updated during 2023 as key
equipment has been re-tendered. The cost estimate will be refined and updated prior to the
decision to commence construction.
Major Equipment Procurement
VRX has prepared a summary of the major long lead time equipment that will be procured and
has recently refreshed the quotations for most of these items. Some equipment has not been
retendered for some time and will require retendering closer to the execution phase. Timing
for procurement is subject to the EPA approvals process.
When evaluating tenders VRX uses a Tender Evaluation (TEV) process to summarise the
tender submissions and to essentially land on the preferred tender.
Short Term Ongoing Works
VRX intends to carry on with the following development tasks.
•
Rearrange the execution cost estimate to show costs by area rather than by task, for
inclusion in the data room for DD by financiers. This is a short-term priority.
•
Evaluate recent retendering of key major equipment and follow up on other equipment
that has not been retendered recently.
•
Continuously update a summary of lead times for major equipment suppliers to carry
out the detailed design of their equipment, in order to reduce their equipment lead
times.
•
Continue to refine the execution cost estimate in light of recent retendered equipment
and other information.
•
Refine the execution schedule estimate in light of recent retendered equipment and
other information.
•
Produce a manning histogram for the execution phase and investigate accommodation
planning as necessary.
•
Review the Operating & Control Philosophy.
•
Liaise with the power provider to assist with the development of the preferred power
option
12
Figure 5: Feed Trommel
Figure 6: Schenk vibrating banana screen
13
Strategic Research Initiative With UNSW
In June 2023 VRX announced a new partnership agreement with the School of Photovoltaic
and Renewable Energy Engineering (SPREE) of the University of New South Wales (UNSW),
on a strategic research project investigating the market potential for a local, low carbon, solar
panel glass recycling program in Australia. .
The pilot phase of this work received funding from the Australian Renewable Energy Agency
(ARENA), carried out through the Australian Centre for Advanced Photovoltaics (ACAP) at
UNSW. ACAP is now able to take this work to its next phase with the support of a highly
credentialed industry partner specialising in the sustainability of the material critical to solar
panel production – silica sand, which is becoming increasingly scarce.
To advance the sector’s sustainability, the project will perform a techno-economic analysis of a
proposed closed-loop photovoltaic (PV) glass industry in Australia, built on recycling the glass
component of solar panels once they reach their end-of-life. A necessary condition for this
industry will be the recreation of a local, low-iron, flat glass manufacturing industry, where solar
panel cover glass could be returned as cullet (crushed glass).
Specifically, the agreement aims to support modelling of possible low-iron glass recycling and
manufacturing pathways in Australia, with activities potentially located near Muchea.
VRX is pleased to collaborate with the University of New South Wales and the Australian
Renewable Energy Agency in this initiative to investigate the potential recycling of components
of solar panels.
This part of the life cycle of a solar panel is insufficiently studied but is increasingly required to
complete the cycle for the use of solar panels.
How Solar Panel Glass Recycling Could Work in Australia
The silica sand at Muchea, in particular, has very low iron content, making it highly suitable for
use in manufacturing solar panel glass. Existing rail access increases the feasibility of the lowcarbon transport of sand to ports for export, or to a nearby future glass factory. It is also suitable
for the transport of cullet from all over Australia to a potential new glass factory.
Basic methods have already been established for separating PV cover glass from other module
materials, with some already in use in Australia, or with orders having been placed for
equipment to do so.
VRX will share data with ACAP researchers on its Muchea deposit, including all related to
progress made towards the development of the deposit, the requirements for sand, cullet and
other input materials for low-iron glass manufacture in Western Australia, and information about
global sand availability and value, as well as broader industry insights on the glass
manufacturing sector.
UNSW will provide information on PV glass recovery activities in Australia and elsewhere,
including projected glass demand for the global PV industry and the results of techno-economic
modelling.
The project term is two years commencing 1 July 2023. There is no cash funding obligation on
VRX.
14
Extension of Xodus MOU
In June 2023 agreed a six month extension of its non-binding memorandum of understanding
(MOU) with Xodus Group Pty Ltd (Xodus) to 31 December 2023. First announced in March
2022, the MOU seeks to explore the future supply of renewable hydrogen to the Company’s
silica sand projects as well as to potential, nearby glass-manufacturing facilities to enable the
production of net-zero glass.
Xodus, a global energy consultancy, specialises in the integration of environmental science,
engineering and management to provide holistic support and services in energy transition. An
Xodus-led consortium is developing Project MercurHy for the industrial-scale production of
hydrogen gas using renewable energy in the Mid West region of Western Australia.
The MOU with Xodus establishes a platform for strategic confidential communication and
future co-operation between the parties. It contemplates the sharing of information with a view
to a future offtake of between 9,000 tonnes to 11,000 tonnes of hydrogen per annum, which
is adequate to supply a substantial glass-making facility.
Corporate
During the quarter under review the Company issued 7,200,000 options under its Employee
Incentive Scheme. The options were issued on 30 May 2023, have an exercise price of 15c
and an expiry date of 31 December 2026. The options will remain unlisted and no funds were
raised from their issue.
Events Subsequent to the End of the Quarter
$2 million Investment Attraction Fund Grant
On 18 July 2023 VRX announced it had received confirmation from the Western Australian
State Government that the Company’s grant application for $2 million in matched funding
under the Investment Attraction Fund (IAF) has been approved with a Financial Assistance
Agreement (FAA) for the grant executed that day.
The IAF is part of the State Government’s Diversify WA initiative, a collaboration between
government, industry and the community supporting the WA Government’s focus on creating
secure, quality jobs, growing and diversifying the economy and attracting new investment.
The grant under the IAF is being awarded on a matched funding, dollar for dollar basis,
whereby the IAF will provide a financial contribution to VRX up to $2m.
The project proposed by VRX will investigate the potential to develop a high purity quartz (or
HPQ) flour manufacturing process and pilot plant in Western Australia, which if successful will
lead to the development of a larger commercial plant for large scale processing.
VRX intends to develop a High Purity Quartz flour manufacturing process to meet a standard
of 99.999% SiO2 (5N) purity. This involves the establishment of a new lower purity quartz
resource to be beneficiated in quality, allowing a new manufacturing process tailored to
beneficiating the purity of Western Australia quartz and finally the establishment of the high
purity quartz flour manufacturing plant and the associated supply chains.
The key objective of this project is to commercialise the manufacturing process of High Purity
Quartz flour within Western Australia. This will involve sourcing and beneficiating the purity of
lower quality quartz through primarily mechanical and possibly chemical processes. The
15
establishment of a process and purity standard has the potential to lead to a manufacturing
facility, commercial partners and a supply chain for the critical minerals.
The three main objectives for the project are:
•
To determine the key elements that would lead to the successful commercialisation of a
manufacturing process to beneficiate the quality of the lower purity quartz (99.9% SiO2) to
a higher silica grade.
•
To complete a pre-feasibility study that would determine the grade of quartz and
processing method that could feasibly be manufactured from its existing feedstocks with a
target of reaching 99.999% SiO2 purity quartz flour.
•
To establish a full-scale manufacturing plant to process the resource into high purity quartz
flour utilising the work from the previous objectives, testwork and marketing carried out as
a backbone to support the future work to be carried out.
The HPQ market is one of growing demand but with a relatively small supplier base.
Initially, VRX will investigate the potential for the coarse material that will be produced from
Muchea. Recent pilot plant work completed on a 2.2 tonne bulk sample of Muchea sand
indicated that a portion of project ore may meet the specification required.
Whilst the goal is to achieve the high-quality required, by raising its high-grade silica sand
resource from Muchea to at least “4 nines” (ie. 99.99% SiO2 purity) it would still allow a wide
range of high demand large-value products to be made. This includes use as a feed material
for several industries and downstream products including paint fillers, fibre glass, water purity
media, and silica flour for the production of LCDs and silica gels.
Arrowsmith Brand Mining Lease
On 19 July 2023 VRX announced the grant of a Mining Lease (M70/1418) at Arrowsmith
Brand. Details of the project and the tenement are set out above.
Geothermal Exploration Permit
On 28 July 2023 VRX announced it had been granted Geothermal Exploration Permit (GEP)
GEP 44 consisting of 8 blocks at Dandaragan, 145km north of Perth, Western Australia.
Geothermal technology has the potential to produce long term dispatchable renewable energy
for the Mid-West region, including the Arrowsmith Silica Sand Projects, as well as green
hydrogen for the manufacture of glass.
The Dandaragan GEP area includes the Walyering gas field currently under development by
EP447 Joint Venture between Strike Energy 55% and Talon Energy 45%. The grant presents
an opportunity to work with these companies to use extensive historical and current data to
explore for potential geothermal power options.
The grant follows the acreage release nomination VRX lodged in December 2021 and
subsequent GEP application in April 2022 with DMIRS. The Comp