Half Yearly Report and Accounts
Released
Released
Announcement PDF
VRX SILICA LIMITED
ABN 59 142 014 873
INTERIM FINANCIAL REPORT
FOR HALF-YEAR ENDED
31 DECEMBER 2020
CORPORATE DIRECTORY
DIRECTORS
Paul Boyatzis (Non-Executive Chairman)
Bruce Maluish (Managing Director)
Peter Pawlowitsch (Non-Executive Director)
SECRETARY
John Geary
REGISTERED AND PRINCIPAL OFFICE
Level 1, 6 Thelma Street
West Perth WA 6005
Telephone: (08) 9226 3780
Facsimile: (08) 9226 3764
Website:
www.vrxsilica.com.au
SHARE REGISTRY
Computershare Investor Services Pty Ltd
Level 11, 172 St George's Terrace
Perth WA 6000
Telephone: (08) 9323 2000
Facsimile: (08) 9323 2033
AUDITORS
RSM Australia Partners
Level 32, Exchange Tower
2 The Esplanade
Perth WA 6000
AUSTRALIAN SECURITIES EXCHANGE
VRX Silica Limited shares (VRX) are listed on the
Australian Securities Exchange
VRX Silica Limited
1
DIRECTORS’ REPORT
Your directors submit the financial report of the consolidated entity for the half-year ended 31
December 2020. In order to comply with the provisions of the Corporations Act 2001, the
directors report as follows:
DIRECTORS
The names of the Directors who held office during or since the end of the half-year and until
the date of this report are noted below. Directors were in office for this entire period unless
otherwise stated:
Paul Boyatzis (Non-Executive Chairman)
Bruce Maluish (Managing Director)
Peter Pawlowitsch (Non-Executive Director)
PRINCIPAL ACTIVITIES
The principal continuing activities during the half-year of entities within the consolidated entity
was mineral exploration.
REVIEW OF OPERATIONS
The net loss for the half-year attributable to members of VRX Silica Limited was $822,135
(2019: loss of $1,379,165).
The following is a summary of the activities conducted by VRX Silica Ltd (VRX or Company)
(ASX: VRX) during the half year ending 31 December 2020.
Arrowsmith Silica Sand Projects
Native Title Clearance
VRX holds the Arrowsmith North and Arrowsmith Central Silica Sand Projects (Arrowsmith
Projects), which are located 270km north of Perth, Western Australia, in its wholly owned
subsidiary Ventnor Mining Pty Ltd.
In October 2020, conclusive registration of the Yamatji Nation Indigenous Land Use Agreement
(ILUA) occurred, which cleared the path for grant of the Company’s Mining Lease and
Miscellaneous Licence applications for its Arrowsmith Projects.
The ILUA is an alternative settlement by the West Australian Government of Native Title claims
covering a significant portion of land in the Mid West, including the Southern Yamatji People’s
claim covering the Arrowsmith Projects.
This Government-led ILUA settled all Native Title claims over the Arrowsmith Projects area and
superseded the negotiations that had been progressing in good faith between VRX and the
Southern Yamatji People Native Title claimants over the Arrowsmith Projects. The strong and
supportive relationships established with the Southern Yamatji People will continue to benefit
all parties as the Arrowsmith Projects are developed, and the Company intends to continue to
consult and work closely with the Southern Yamatji People.
VRX Silica Limited
2
DIRECTORS’ REPORT
Aboriginal Heritage Survey
In November 2020, VRX announced the results of an Aboriginal heritage survey at its
Arrowsmith Projects.
The comprehensive archaeological and ethnographic survey was conducted during October in
conjunction with Amangu representatives of the Yamatji Nation and Yamatji Marlpa Aboriginal
Corporation (YMAC) personnel over proposed initial mining and critical infrastructure areas.
The survey found no isolated artifacts and no onerous heritage recommendations were made.
Preliminary advice received by the Company from YMAC confirmed that the Arrowsmith North
Access Road, Services Corridor and Production Area have been approved for the stated works
to proceed for 10 years of production. The Arrowsmith Central Production Area and Arrowsmith
Central Infrastructure Areas are cleared for five years of production. See Figure 1.
Figure 1: Critical infrastructure and mining areas surveyed at Arrowsmith Projects
VRX Silica Limited
3
DIRECTORS’ REPORT
Grant of Mining Leases
On 17 November 2020, VRX announced the grant of Mining Leases for its Arrowsmith Projects
(see Figure 2). This, together with the Aboriginal heritage clearance for the proposed works
on both projects, is an important step forward for their development. The combined Mining
Lease areas cover over 3,600ha, sufficient for more than 100 years of production.
The grant of these Mining Leases was another significant milestone for the Company and came
shortly after the grant of the Mining Lease for VRX’s Muchea Silica Sand Project (Muchea
Project) (see below). It enables the Company to step up negotiations to finalise sales contracts
for the high-quality silica sand products and secure the necessary funding for their
development.
Figure 2: Arrowsmith Silica Sand Projects Location
VRX Silica Limited
4
DIRECTORS’ REPORT
Environmental Approval
As part of the environmental approvals process for the grant of a Mining Permit at the
Arrowsmith Projects, the Company continued to compile the necessary data to support the
Environmental Referral Document (ERD) referrals to the Federal Department of Agriculture,
Water and Environment (DAWE) and the State Department of Water and Environmental
Regulation (DWER). The Company and its environmental consultants held pre-referral
meetings with representatives from DWER and received comments regarding further
requirements for the referral. Pre-referral meetings with representatives from DAWE and the
DWER provided valuable feedback regarding requirements for these referrals.
During the half-year period, VRX submitted a formal Environmental Review Document to
DAWE for assessment under the Environmental Protection and Biodiversity Conservation Act
1999 (EPBC Act). DAWE responded with a determination that Arrowsmith North was a
controlled action subject to assessment by DWER and approval under the EPBC Act before it
can proceed.
In October 2020, VRX submitted a draft ERD to DWER with comments returned in November
2020 requiring further clarification in the formal ERD and follow-up work and consultation.
VRX anticipates submitting its formal ERD to DWER in March 2021 as part of the process to
secure environmental approvals for the development of Arrowsmith North.
Since the end of the review period, in February 2021 VRX received approval to conduct a trial
rehabilitation program over 7,200m2. VRX proposes to trial and video a front-end loader to
establish the capability of removing and replacing sods of topsoil as proposed in our mining
and rehabilitation methodology. The front-end loader will be equipped with a standard sand
bucket, not the proposed modified bucket. The trial will be undertaken between late March
and April 2021.
In parallel with the environmental approval process, the Company will seek approval for its
Mining Proposal and the issue of a mining permit from the Department of Mines, Industry
Regulation and Safety (DMIRS).
Muchea Silica Sand Project
On 29 October 2020, VRX announced the grant of a Mining Lease for its Muchea Silica Sand
Project (Muchea Project), located 50km north of Perth, Western Australia. The Mining Lease
(M70/1390), held in the Company’s wholly owned subsidiary Wisecat Pty Ltd, covers
approximately 1,008ha including the development area, sufficient for at least 25 years of
production (see Figure 3).
The grant of the Mining Lease was a significant milestone for VRX and a major step forward in
the Company’s journey to becoming a global, long-life supplier of high-quality silica sand.
During the period, as for its Arrowsmith Projects, the Company progressed compilation of
necessary data to support referrals to DAWE and the EPA with pre-referral meetings held with
representatives from DAWE.
Demand from potential customers for long-term supply of silica sand from the Muchea Project
is strong. As with the Arrowsmith Projects, the grant of the Mining Lease enables the Company
to step up negotiations to finalise sales contracts for the high-quality silica sand products and
secure the necessary funding for the project’s development.
VRX Silica Limited
5
DIRECTORS’ REPORT
The Muchea Project is a world-class, high-grade and low environmental impact silica sand
project with outstanding economics and located in a Tier 1 jurisdiction. Its development will
support a substantial export industry in Western Australia and provide significant financial and
employment benefits in the north-eastern corridor of Perth.
Figure 3: Muchea Silica Sand Project Location
VRX Silica Limited
6
DIRECTORS’ REPORT
Silica Sand Offtake
The Company has continued discussions with potential customers in Asia for long-term
contracts for offtake of products from its Arrowsmith Projects and Muchea Project. These
customers are in Malaysia, Thailand, Taiwan, Japan and South Korea.
The outbreak of COVID-19 in early 2020 caused the cessation of all possible face-to-face
meetings with potential clients. However, the Company has progressed discussions via video
conferencing and interest remains strong, despite the current challenging health and economic
climate in those countries. More recently second and third-wave lockdowns in Japan and Korea
have further postponed offtake discussions, with no possibility for VRX to conduct face-to-face
meetings.
Despite the COVID-19 impediment, global market conditions continued to improve over the
period. Sources of supply of high-quality silica sand throughout the Asian region are shrinking
at a rapid rate and increasing the already strong demand for VRX’s silica sand products,
providing the Company with comfort its considered and disciplined approach to offtake deals
will deliver significant value to shareholders.
Product samples have been shipped to potential offtake partners and grade-control drilling
planned for March 2021 will generate additional commercial samples for interested parties.
The majority of recipients have confirmed that the sand quality meets their specification
requirements and underpins their desire to secure long-term supply.
The Company is well-positioned to benefit from the rapidly changing, and improving, market
conditions and will continue negotiations to secure formal offtake agreements.
Project Economics
The Company’s silica sand projects have outstanding economic prospects and will support a
substantial export industry in Western Australia that can provide significant financial and
employment benefits to the State.
With all three Mining Leases granted at the Arrowsmith Projects and the Muchea Project and
development of the projects on-track, VRX is on the cusp of becoming a global player in highquality silica sand supplies.
ARROWSMITH NORTH
Project Location
Arrowsmith North is located approximately 270km north of Perth between the regional towns
of Eneabba and Dongara (see Figure 1 and Figure 2). The project sits proximate to Brand
Highway and is connected to the Geraldton Port via the Eneabba-Geraldton Railway.
VRX Silica Limited
7
DIRECTORS’ REPORT
Mineral Resource and Ore Reserve
The Mineral Resource Estimate (MRE) for Arrowsmith North comprises an Indicated Mineral
Resource of 248 Mt @ 97.7% SiO2 in addition to an Inferred Mineral Resource of 523 Mt
@ 98.2% SiO2 for a Total MRE of 771 Mt @ 98.0% SiO2 1 reported in accordance with the
JORC Code 2 (Table 1).
Classification
Domain
Million Tonnes
SiO2%
Al2O3%
Fe2O3%
TiO2%
LOI%
Indicated
White Sand
33
98.7
0.50
0.20
0.20
0.20
Yellow Sand
215
97.5
1.10
0.40
0.20
0.50
All Sand
248
97.7
1.00
0.40
0.20
0.50
White Sand
280
98.7
0.50
0.10
0.20
0.20
Yellow Sand
243
97.7
1.00
0.40
0.20
0.50
All Sand
523
98.2
0.80
0.30
0.20
0.40
White Sand
313
98.7
0.54
0.15
0.18
0.24
Yellow Sand
458
97.6
1.08
0.40
0.17
0.52
All Sand
771
98.0
0.86
0.30
0.17
0.41
Inferred
Indicated +
Inferred
*Note: Interpreted silica sand mineralisation is domained above a basal surface wireframe defined based on drill logging data. The
upper (Topsoil) layer within 0.5 m of surface is depleted from the modelled silica sand unit, being reserved for rehabilitation
purposes. All classified silica sand blocks in the model are reported. Differences may occur due to rounding.
Table 1: Arrowsmith North Mineral Resource Estimate
The Company completed the necessary work to convert the Indicated Mineral Resource to a
Probable Ore Reserve 3. Table 2 details the Probable Ore Reserve reported in accordance
with the JORC Code that will be produced from mining of the Indicated Mineral Resource and
processing in a purpose-built, wet-sand processing plant.
Recovery
Million
Tonnes
Within
M70/1389
Million
Tonnes
Arrowsmith-N20
24%
60
54
99.7
0.2
0.05
0.035
0.1
Arrowsmith-N40/
NF500
60%
149
136
99.7
0.2
0.05
0.035
0.1
Local Market
6%
15
14
223
204
Global
Chemical Composition
Classification
Probable
Product
Total Reserve
SiO2
%
Al2O3
%
Fe2O3
%
TiO2
%
LOI
%
Table 2: Arrowsmith North Probable Ore Reserve
Production Target
The Company set out in the Arrowsmith North bankable feasibility study (BFS) a production
target of 47.7Mt from the first 25 years of mine life at Arrowsmith North, reported in accordance
with the JORC Code and sourced from the Probable Ore Reserve of 204Mt @ 99.7% SiO2
within the Mining Lease (M70/1389) area.
Full details are set out in the Arrowsmith North BFS 4.
1 ASX announcement of 9 July 2019, “Arrowsmith North Mineral Resource Estimate Upgrade”
2 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves, 2012 Edition
(JORC Code).
3 ASX Announcement of 28 August 2019, “Arrowsmith North BFS and Maiden Ore Reserve”
4 ASX Announcement of 28 August 2019, “Arrowsmith North BFS and Maiden Ore Reserve”
VRX Silica Limited
8
DIRECTORS’ REPORT
Silica Sand Products
Based on metallurgical test work completed to date, the silica sand at Arrowsmith North is
readily amenable to upgrading by conventional washing and screening methods to produce a
high-purity silica sand product with high-mass recoveries. The high-purity silica sand product
specifications are expected to be suitable for industries such as glass making and foundry
sand. The plant will produce four saleable products for different markets. Table 3 shows the
particle-size distribution of the products.
Particle Size
Sieve Opening (Mesh/μm Retained)
Product
10 /
2mm
20 /
850
30 /
600
40 /
425
50 /
300
70 /
212
140 /
106
0.10%
100 /
150
-
AFS
No
-
200 /
75
-
Arrowsmith-N20
0.10%
3%
87%
8%
1%
Arrowsmith-N40
-
0%
21%
36%
24%
13%
5%
1%
0%
36
Arrowsmith-NF500
-
-
0.50%
40%
42%
17%
1%
0%
-
38
Local Market
-
-
-
-
-
-
64%
22%
14%
-
21
Table 3: Arrowsmith North saleable products, particle size distribution
ARROWSMITH CENTRAL
Project Location
Arrowsmith Central is located approximately 270km north of Perth between the regional towns
of Eneabba and Dongara (see Figure 1 and Figure 2). The project sits proximate to Brand
Highway and is connected to the Geraldton Port via the Eneabba-Geraldton Railway.
Mineral Resource and Ore Reserve
The Mineral Resource Estimate (MRE) for Arrowsmith Central comprises an Indicated Mineral
Resource of 28.2 Mt @ 96.6% SiO2 in addition to an Inferred Mineral Resource of 48.3 Mt
@ 96.9% SiO2, for a Total MRE of 76.5 Mt @ 96.8% SiO2 5 reported in accordance with the
JORC Code (Table 4).
Classification
Million Tonnes
SiO2%
Al2O3%
Fe2O3%
TiO2%
LOI%
Indicated
28.2
96.6
1.7
0.4
0.2
0.7
Inferred
48.3
96.9
1.5
0.4
0.2
0.7
Indicated + Inferred
76.5
96.8
1.5
0.4
0.2
0.7
* Note: Interpreted silica sand mineralisation is domained above a basal surface wireframe defined based on drill sampling
depths. A depletion zone, consisting of the upper 0.5 m, is reserved for rehabilitation purposes and is not estimated or reported.
Differences may occur due to rounding.
Table 4: Arrowsmith Central Silica Sand Mineral Resource Estimate
The Company has completed the necessary work to convert the Indicated Mineral Resource
to a Probable Ore Reserve. Table 5 below details the Probable Ore Reserve that will be
produced from the mining of the Indicated Mineral Resource and processing in a purposebuilt, wet-sand processing plant.
5 ASX announcement of 15 August 2019, “Arrowsmith Central Mineral Resource Estimate Upgrade”.
VRX Silica Limited
9
DIRECTORS’ REPORT
Product
Recovery
Million
Tonnes
Within
M70/1392
Million
Tonnes
Arrowsmith-CF400
17%
4.2
4.1
Arrowsmith-C20
34%
8.4
8.2
Arrowsmith-C50
17%
4.2
4.1
TiO2 Concentrate
9%
2.2
2.2
18.9
18.7
Global
Chemical Composition
Classification
Probable
Total Reserve
SiO2
%
Al2O3
%
Fe2O3
%
TiO2
%
LOI
%
99.6
0.25
0.04
0.03
0.1
<1%
+2%
Table 5: Arrowsmith Central Probable Ore Reserve
Production Target
The Company has set out in the Arrowsmith Central BFS a production target of 18.9 Mt @
99.6% SiO2 as reported in accordance with the JORC Code with 18.7 Mt @ 99.6% SiO2
contained within the area of the Company’s Mining Lease (M70/1392).
Full details are set out in the Arrowsmith Central BFS 6.
Silica Sand Products
Based on metallurgical test work completed to date, the silica sand at Arrowsmith Central is
readily amenable to upgrading by conventional washing and screening methods to produce a
high-purity silica sand product with high-mass recoveries. The high-purity silica sand product
specifications are expected to be suitable for industries such as glass making and foundry
sand.
The plant will produce three saleable silica sand products for different markets. Table 6 shows
the particle-size distribution of the products.
Particle Size
Sieve Opening (Mesh / μm Retained)
Product
10 /
2mm
20 /
850
30 /
600
40 /
425
50 /
300
70 /
212
140 /
106
16.1%
100 /
150
0.5%
Arrowsmith-CF400
-
0%
0.5%
44%
38.9%
Arrowsmith-C20
6.2%
22.2%
30.4%
37.9%
Arrowsmith-C50
-
-
0.3%
31.9%
AFS
No
-
200 /
75
-
2.9%
0.3%
0.1%
-
-
22
27.5%
17.3%
13.7%
8.2%
1.1%
49
37
Table 6: Arrowsmith Central Silica Sand Probable Ore Reserve
In addition to these products, the plant will produce a by-product that contains a concentration
of titanium minerals such as rutile and ilmenite, which can be sold at a nominal value to a
company with specialist equipment for separating mineral concentrate (see Table 5 for
summary of TiO2 concentrate).
6 ASX Announcement of 17 September 2019, “Arrowsmith Central BFS and Maiden Ore Reserve”
VRX Silica Limited
10
DIRECTORS’ REPORT
MUCHEA
Project Location
The Muchea Project is located 50km north of Perth between the regional towns of Muchea
and Gingin (see Figure 3) and sits adjacent to Brand Highway and the Moora–Kwinana
Railway, with a rail connection direct to the multi-user Kwinana Bulk Terminal.
Mineral Resource and Ore Reserve
The Mineral Resource Estimate (MRE) for the Muchea Project comprises 208Mt @ 99.6%
SiO2 7 reported in accordance with the JORC Code 8 (Table 7).
The MRE is based on the results obtained from 44 hand auger drill holes for 260.7m and 103
air core (AC) drill holes for 1,401m used to define the modelled silica sand layer.
Classification
Million Tonnes
SiO2%
Al2O3%
Fe2O3%
LOI%
TiO2%
Indicated
29
99.6
0.09
0.03
0.22
0.07
Inferred
179
99.6
0.05
0.02
0.23
0.1
Indicated + Inferred
208
99.6
0.06
0.02
0.23
0.1
*Note: Interpreted silica sand mineralisation is domained above a basal surface wireframe. The upper (overburden)
layer within 0.5 m of surface is depleted from the modelled silica sand unit, being reserved for rehabilitation purposes.
All classified silica sand blocks in the model are reported. Differences may occur due to rounding.
Table 7: Muchea Mineral Resource Estimate
The Company has completed the necessary work to convert the Indicated Mineral Resource to
Probable Ore Reserve 9. Table 8 details the Probable Ore Reserve reported in accordance with
the JORC Code that will be produced from mining of the Indicated Mineral Resource and
processing in a purpose-built, wet-sand processing plant.
Product
Recovery
Million
Tonnes
Within
M70/1390
Million
Tonnes
Muchea-F80
48%
10.2
8.0
+99.9
0.02
0.008
0.030
0.1
Muchea-F80C
20%
4.25
3.3
+99.9
0.02
0.008
0.030
0.1
Muchea-F150
20%
4.25
3.3
99.8
0.07
0.015
0.035
0.1
18.7
14.6
Global
Ore Reserve
Classification
Probable
Total Reserve
SiO2
%
Al2O3
%
Fe2O3
%
TiO2
%
LOI
%
Table 8: Muchea Silica Sand Probable Ore Reserve
Initial Production Target
The Company has set out in the BFS an initial production target of 48.3Mt from the Muchea
Project reported in accordance with the JORC Code, sourced from the Probable Ore Reserve
of 14.6Mt @ 99.9% SiO2 and a portion of the Inferred Mineral Resource of 61.4Mt @ 99.6%
SiO2 within the Mining Lease area.
7 ASX announcement of 17 June 2019, “Muchea Mineral Resource Estimate Upgrade”.
8 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves, 2012 Edition
(JORC Code).
9 ASX Announcement of 18 October 2019, “Muchea BFS and Maiden Ore Reserve”
VRX Silica Limited
11
DIRECTORS’ REPORT
The maiden Probable Ore Reserve is estimated from the Indicated Mineral Resource only and
constitutes approximately 30% of the estimated total production target (in terms of processed
tonnes of silica sand) over a 25-year mine life. The Company intends to mine solely from the
Probable Ore Reserve during the first nine to 10 years of mining operations.
The ore that forms the Inferred Mineral Resource is contiguous with the Indicated Mineral
Resource and has been categorised as lower confidence because of wider-spaced drilling.
There is negligible difference between the modelled sand in each category. VRX believes an
additional 1,500m of drilling is required to upgrade the inferred resource category.
Notwithstanding this, there is a low level of geological confidence associated with inferred
mineral resources and no certainty that further exploration work will result in the determination
of indicated mineral resources or that the production target itself will be realised.
Full details are set out in the BFS. 10
Silica Sand Products
Based on metallurgical test work completed to date, the silica sand at Muchea is readily
amenable to upgrading by conventional washing and screening methods to produce a highpurity silica sand product with high-mass recoveries. The high-purity silica sand product
specifications are expected to be suitable for industries such as glass making and foundry
sand.
The plant will produce three saleable products for different markets with a Probable Ore
Reserve of 14.6Mt @ 99.9% SiO2 reported in accordance with the JORC Code and contained
within the area of the Mining Lease.
Table 9 shows the particle-size distribution of the products.
Particle Size
Product
Sieve Opening (μm Retained)
850
Muchea-F80
Muchea-F80C
9.0%
600
425
300
212
0.5%
49%
50%
0.5%
90.0%
1.0%
0.5%
88%
Muchea-F150
150
106
11%
0.5%
75
Table 9: Muchea saleable products, particle size distribution
Potential for Extension of Life of Mine
Mining Lease M70/1390 is a conversion of part of Exploration Licence E70/4886, which covers
a portion of file notation area 12671 (FNA). The FNA ground within the Exploration Licence
sits adjacent to the Mining Lease and outside of the current proposed development area and
does not affect the BFS-modelled 25-year production life.
VRX intends to seek access to this ground to extend the Muchea Project’s mine life to well
beyond 25 years. To that end, the Company will continue to assess available options while
addressing concerns relating to the FNA.
10 ASX Announcement of 18 October 2019, “Muchea BFS and Maiden Ore Reserve”
VRX Silica Limited
12
DIRECTORS’ REPORT
Key outcomes from Muchea Project BFS
The Muchea Project has outstanding economic prospects. Key outcomes from the BFS 11 and
summary financial model outputs are set out below.
Muchea
(including Inferred)
Muchea
(Reserve only)
Post Tax, ungeared NPV10
$337,900,000
$180,500,000
Post Tax, ungeared NPV20
$146,400,000
$104,600,000
Post Tax, ungeared IRR
96%
96%
Payback period (yrs) (post tax) (ramp up rate)
2.3
2.3
Exchange Rate US$/A$
$0.70
$0.70
Life of Mine (yrs) (Scope of BFS Study)
25
15
Total Sales (initial 25 years) no escalation
$3,345,000,000
$1,011,000,000
EBIT
$1,540,000,000
$447,000,000
Cashflow after finance and tax
$1,123,000,000
$321,000,000
Shares on Issue
404,318,617
404,318,617
$0.11
$0.09
$32,820,000
$32,820,000
Capex contingency (inc)
20%
20%
Life of Mine C1 costs, FOB Kwinana (inc royalties)
$32.74
$33.84
54
16
EPS after tax (per year)
Capex (2 mtpa)
Tonnes Processed (initial 25 years) (Mt)
Production Target (Mt) (BFS Study)
(25 years) 48.3
(9-10 years) 14.6
Probable Ore Reserves @ 99.9% SiO2 (Mt)
18.7
18.7
Ore Reserve life (yrs)
9-10
9-10
JORC Resources (million tonnes)
208
208
Notes:
1. The first column shows outputs when aggregated with the Inferred Mineral Resource and the second column
shows outputs from the Probable Ore Reserve only.
2. There is a low level of geological confidence associated with inferred mineral resources and there is no certainty
that further exploration work will result in the determination of indicated mineral resources or that the production
target itself will be realised.
3. The Probable Ore Reserve and the Inferred Mineral Resource underpinning the above production targets have
been prepared by a Competent Person in accordance with the requirements of the JORC Code.
4. Full summaries of economic assumptions are set out in the BFS. All such material assumptions continue to apply
and have not materially changed from the date of release of the BFS.
5. All figures are presented in Australian dollars, unadjusted for inflation.
11 ASX Announcement of 18 October 2019, “Muchea BFS and Maiden Ore Reserve”
VRX Silica Limited
13
DIRECTORS’ REPORT
Aggregate Project Metrics
Key outcomes and summary financial model outputs for each individual project, and in
aggregate, from the BFSs for each project 12 are set out below. The combined post-tax NPV10
of $727.8 million
Arrowsmith North Arrowsmith Central
Muchea
Total
Post Tax, ungeared NPV10
$242.3m
$147.6m
$337.9m
$727.8m
Post Tax, ungeared NPV20
$99.8m
$56.1m
$146.4m
$302.3m
Post Tax, ungeared IRR
79%
60%
96%
83%
Payback period (yrs) (post tax) (ramp up rate)
2.4
2.8
2.3
2.4
Exchange Rate US$/A$
$0.70
$0.70
$0.70
$0.70
Life of Mine (yrs) (Scope of BFS Study)
25
25
25
25
Total Sales (initial 25 years) no escalation
$2,773m
$2,167m
$3,345m
$8,285m
EBIT
$1,144m
$737m
$1,540m
$3,421m
Cashflow after finance and tax
$835m
$539m
$1,123m
$2,497m
Capex (2 mtpa)
$28.3m
$25.9m
$32.8m
$87m
Capex contingency (inc)
20%
20%
20%
20%
Life of Mine C1 costs, FOB Kwinana (inc royalties)
$30.18
$27.67
$32.74
$30.24
Tonnes Processed (initial 25 years) (Mt)
53
51
54
158
Production Target (Mt) (BFS Study) (initial 25 Years)
47.7
39.6
48.3
136
Probable Ore Reserves (Mt)
204
18.9
18.7
242
Ore Reserve life (yrs)
102
10
9-10
JORC Resources (million tonnes)
771
77
208
1,056
Notes:
1. A proportion of the production target for each of Arrowsmith Central and Muchea is based on Inferred Mineral
Resource. There is a low level of geological confidence associated with inferred mineral resources and there is no
certainty that further exploration work will result in the determination of indicated mineral resources or that the
production target itself will be realised.
2. The Ore Reserves and, in the case of Arrowsmith Central and Muchea, the Inferred Mineral Resource underpinning
the above production targets have been prepared by a Competent Person in accordance with the requirements of the
JORC Code.
3. Full summaries of economic assumptions are set out in the BFS for each project. All such material assumptions
continue to apply and have not materially changed from the dates of release of the BFSs.
4. All figures are presented in Australian dollars, unadjusted for inflation.
12 ASX announcements of 28 August 2019, “Arrowsmith North BFS and Maiden Ore Reserve”,
17 September 2019, “Arrowsmith Central BFS and Maiden Ore Reserve” and
18 October 2019, “Muchea BFS and Maiden Ore Reserve”.
VRX Silica Limited
14
DIRECTORS’ REPORT
Biranup
On 1 July 2020, the Company announced it had entered into a conditional agreement with
New Energy Metals Limited (to be renamed Nickel X Limited) for the sale of its Biranup Project
and an IPO and listing of that company on the ASX.
Originally expected to complete by the end of 2020, increasing activity for new ASX listings
generally has delayed progress on the IPO. The Company has agreed a new completion
sunset date of 30 June 2021, subject to minimum exploration expenditure obligations being
satisfied by the purchaser in Q1 2021.
Corporate
On 20 November 2020, VRX announced that it had received binding commitments for a capital
raising via a share placement to institutional, professional and sophisticated investors to raise
$7 million before costs.
VRX received strong support for the capital raising from a wide range of investors, with bids
received well in excess of the amount raised.
This placement positioned VRX to rapidly advance the development of its silica sand projects,
in particular at Arrowsmith North for grade-control drilling for the first 10 years of production,
confirmatory test work, drilling and equipping water bores, port access design, construction of
access roads and final engineering.
The placement was conducted at 18 cents per share, which represented a 23.4% discount to
the last closing price of VRX shares on ASX of 23.5 cents prior to announcing the placement
and a 13.6% discount to the 10-day volume-weighted average price (VWAP) of 20.8 cents as
at the same date. A total of 38.9 million new shares wer
Share your feedback