Diamond Drilling at Thaduna
Released
Released
Announcement PDF
21 January 2016
ASX ANNOUNCEMENT
DIAMOND DRILLING AT THADUNA
Ventnor Resources Ltd (“Ventnor” or “the Company”) (ASX:VRX) is
pleased to announce results from the recent diamond drill program
aimed at resource definition at the Thaduna/Green Dragon Copper
Project in Western Australia.
ASX: VRX
Capital Structure
The drill program completed by joint venture partner Sandfire
Resources NL (ASX:SFR) at Thaduna comprised six diamond drill
holes and two preliminary RC pre-collars with best results of:
Shares on Issue 137.5 million
TDDD010 11.0 metres @ 4.7% Cu and 19.3 g/t Ag
Market Cap @2.0¢ a share
TDDD013
$2.7 million (Fully Diluted)
6.3 metres @ 6.0% Cu and 28.2 g/t Ag
The program had been planned to target gaps in drill hole coverage
over the main ore body between known mineralisation intercepts. All
holes intersected the target zone (see results below).
Ventnor Managing Director Bruce Maluish said: ”These diamond
holes have intersected the main ore body at Thaduna, with the results
meeting our expectations and confirming the predictability and
consistency that was indicated by previous resource drilling”.
Unlisted Options 13.4 million
Corporate Directory
Paul Boyatzis
Non-Executive Chairman
Bruce Maluish
Managing Director
Peter Pawlowitsch
Non-Executive Director
John Geary
Company Secretary
Company Projects
Thaduna/Green Dragon
Copper Project in the
Doolgunna district, WA
(subject to SFR Farm-in)
Black Dragon Gold project
adjacent to the Tropicana
Gold Mine
Warrawanda Nickel Project
south of Newman, WA
The drill program comprised six holes drilled at dips of 60o-63o, and
to a depth of 462m downhole. The program targeted the Thaduna
Fault mineralisation and was designed to infill the existing drilling and
increases the geological confidence in the area tested. Each drill hole
was designed to improve geological certainty over the areas of known
mineralisation, and to extend mineralisation where possible.
The Company is actively
assessing other base metal
projects in Australia.
Hole Assays
Hole ID
TDDD010
Interval
From (m)
To (m)
Downhole
Width (m)
1
245.0
247.0
2.0
2
272.0
283.0
11.0
TDDD011
1
223.9
224.2
0.3
2
245.0
245.9
0.9
3
297.6
299.0
1.4
4
352.3
353.9
1.6
TDDD012
1
279.0
280.0
1.0
2
288.0
289.0
1.0
3
383.0
386.0
3.0
TDDD013
1
355.7
357.0
1.3
2
381.0
387.3
6.3
TDDD014
1
247.0
251.0
4.0
2
255.8
257.0
1.2
TDDD015
1
225.2
225.7
0.6
2
321.2
323.3
2.1
Intersections calculated above a cut off of 0.7% Cu
Est. True
Width
(m)
1.4
7.5
0.2
0.6
0.9
1.0
0.9
0.9
2.3
0.9
4.4
2.8
0.8
0.4
1.6
Intersection
Cu (%)
Ag (g/t)
1.1
4.7
1.0
4.1
2.1
7.8
2.2
4.9
2.5
2.2
6.0
3.6
1.2
1.2
3.3
3.0
19.3
2.4
1.8
0.3
38.5
0.3
1.1
9.9
5.1
28.2
9.2
3.0
0.3
7.1
Hole Locations
Hole ID
TDDD009
TDDD010
TDDD011
TDDD012
TDDD013
TDDD013A
TDDD014
TDDD015
Depth
66.0
314.3
371.9
462.4
438.3
96.0
300.7
399.6
Dip
-63.0
-61.0
-62.0
-63.0
-63.0
-60.0
-61.0
-61.0
Azimuth
53.4
52.1
60.0
52.0
52.8
51.0
55.0
55.0
Grid ID
MGA94_50
MGA94_50
MGA94_50
MGA94_50
MGA94_50
MGA94_50
MGA94_50
MGA94_50
East
772519
772688
772597
772566
772527
772527
772544
772456
North
7176211
7175878
7175944
7175982
7176029
7176029
7176115
7176146
RL
561.2
560.6
561.8
560.3
560.4
560.5
560.9
560.5
Hole Status
RC Precollar
Complete
Complete
Complete
Complete
RC Precollar
Complete
Complete
Competent Person’s Statement
The information in this release that relates to Exploration Results is based on, and fairly represents,
information compiled by Mr David Reid from information supplied by Sandfire Resources who is a Member
of the Australasian Institute of Mining and Metallurgy (MAusIMM). Mr Reid is a contractor to Ventnor
Resources Limited. Mr Reid has sufficient experience which is relevant to the style of mineralisation and
type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent
Person as defined in the “2012 Edition of the Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves”. Mr Reid consents to the inclusion in this report of the matters based
on information provided by him and in the form and context in which it appears.
For further information please contact:
Bruce Maluish, Managing Director
brucem@ventnorresources.com.au
Tel: +61 8 9226 3780
www.ventnorresources.com.au
Media: Warrick Hazeldine/Luke Forrestal
Cannings Purple
Tel: +61 8 6314 6300
whazeldine@canningspurple.com.au
ABOUT VENTNOR
Ventnor Resources is a base metals focused explorer with a farm-in JV with Sandfire Resources NL at the
historic Thaduna/Green Dragon project, 170 km north of Meekatharra in Western Australia.
The Thaduna/Green Dragon Project is located 40km east of DeGrussa and represents the largest copper
resource in the Doolgunna-Bryah Basin Region outside of Sandfire’s DeGrussa-Doolgunna Project.
The Company has been granted a tenement adjacent to the Tropicana Gold Mine in WA that is prospective
for gold and has had preliminary exploration comprising mapping and rock chip sampling and recently
completed an initial drill program.
Also in Western Australia, 40 km south of Newman is the Warrawanda nickel project.
Known Copper and Nickel Mineralisation
The Thaduna/Green Dragon copper project has historic mine production; copper mineralisation has been
confirmed with four phases of exploration drilling; a Scoping Study has confirmed the economic potential of
the project. A farm-in deal has been transacted with Sandfire Resources to develop the project and to treat
ore. The prospectivity of the Warrawanda nickel project was increased when nickel gossans were identified
in recent work.
Proven Management
The Ventnor directors have extensive experience in the management of publicly listed mining and
exploration companies.
The Company is actively seeking and evaluating other base metals projects in Australia.
PROJECT LOCATIONS
APPENDIX A – JORC 2012 TABLE 1 – EXPLORATION RESULTS
Section 1: Sampling Techniques and Data
Criteria
Sampling
techniques
JORC Code Explanation
Commentary
Nature and quality of sampling (eg cut channels, random chips, or specific
specialised industry standard measurement tools appropriate to the
minerals under investigation, such as down hole gamma sondes, or
handheld XRF instruments, etc). These examples should not be taken as
limiting the broad meaning of sampling.
Sampling method include half-core sampling of NQ2 core diamond drilling (DD).
RC samples are collected by a cone splitter for single metre samples or a sampling spear for first
pass composite samples using a face sampling hammer with a nominal 140mm hole.
Include reference to measures taken to ensure sample representivity and
the appropriate calibration of any measurement tools or systems used.
Sampling is guided by Sandfire protocols as per industry standard.
Aspects of the determination of mineralisation that are Material to the
Public Report.
In cases where ‘industry standard’ work has been done this would be
relatively simple (eg ‘reverse circulation drilling was used to obtain 1 m
samples from which 3 kg was pulverised to produce a 30 g charge for fire
assay’). In other cases more explanation may be required, such as where
there is coarse gold that has inherent sampling problems. Unusual
commodities or mineralisation types (eg submarine nodules) may warrant
disclosure of detailed information.
DD Sample size reduction is through a Jaques jaw crusher to -10mm with a second stage
reduction via Boyd crusher to -4mm. Representative subsamples are split and pulverised
through LM5.
RC sample are crushed to -4mm through a Boyd crusher and representative subsamples
pulverised via LM5.
Pulverising is to nominal 90% passing -75µm and checked using wet sieving technique.
Samples are assayed using Mixed 4 Acid Digest (MAD) 0.3g charge and MAD Hotbox
0.15g charge methods with ICPOES or ICPMS.
Fire Assay is completed by firing 40g portion of the sample with ICPMS finish.
Drill type (eg core, reverse circulation, open-hole hammer, rotary air
blast, auger, Bangka, sonic, etc) and details (eg core diameter, triple or
standard tube, depth of diamond tails, face-sampling bit or other type,
whether core is oriented and if so, by what method, etc).
DD is completed using NQ2 size coring equipment.
RC drilling is with sampling hammer of nominal 140mm hole.
All drill collars are surveyed using RTK GPS with downhole surveying.
All core where possible is oriented using a Reflex ACT II RD orientation tool.
Downhole surveying is undertaken using a gyroscopic survey instrument.
Method of recording and assessing core and chip sample recoveries and
results assessed.
Diamond core recovery is logged and captured into the database. Core recoveries are measured
by drillers for every drill run. The core length recovered is physically measured for each run and
recorded and used to calculate the core recovery as a percentage core recovered.
Drilling techniques
Drill sample
recovery
Criteria
JORC Code Explanation
Commentary
Appropriate measures are taken to maximise sample recovery and ensure the representative
nature of the samples. This includes diamond core being reconstructed into continuous intervals
on angle iron racks for orientation, metre marking and reconciled against core block markers.
RC sampling is good with almost no wet sampling in the project area.
Samples are routinely weighed and captured into the central secured database.
Whether a relationship exists between sample recovery and grade and
whether sample bias may have occurred due to preferential loss/gain of
fine/coarse material.
Whether core and chip samples have been geologically and geotechnically
logged to a level of detail to support appropriate Mineral Resource
estimation, mining studies and metallurgical studies.
No sample recovery issues have impacted on potential sample bias.
Geological logging is completed for all holes and representative across the orebody. The
lithology, alteration and structural characteristics of core are logged directly to a digital format
following procedures and using Sandfire NL geologic codes. Data is imported into Sandfire
NL’s central database after validation in LogChief™.
Whether logging is qualitative or quantitative in nature. Core (or costean,
channel, etc) photography.
Logging is both qualitative and quantitative depending on field being logged.
All cores are photographed.
The total length and percentage of the relevant intersections logged.
All drillholes are fully logged.
If core, whether cut or sawn and whether quarter, half or all core taken.
Core orientation are completed where possible and all are marked prior to sampling. Half core
samples are produced using Almonte Core Saw. Samples are weighed and recorded.
If non-core, whether riffled, tube sampled, rotary split, etc and whether
sampled wet or dry.
RC samples are split using a cone or riffle splitter. A majority of RC samples are dry. On
occasions that wet samples are encountered they are dried prior to splitting with a riffle splitter.
For all sample types, the nature, quality and appropriateness of the sample
preparation technique.
All samples are sorted, dried at 80° for up to 24 hours and weighed. DD samples are crushed
through Jaques crusher to nominal -10mm. A second stage crushing is through Boyd crusher to
nominal -4mm. RC samples are only Boyd crushed to -4mm.
Sample splits are weighed at a frequency of 1:20 and entered into the job results file.
Pulverising is completed using LM5 mill to 90% passing 75%µm using wet sieving technique.
Logging
Sub-sampling
techniques and
sample preparation
Measures taken to maximise sample recovery and ensure representative
nature of the samples.
Quality control procedures adopted for all sub-sampling stages to
maximise representivity of samples.
1:20 grind quality checks are completed for 90% passing 75%µm criteria to ensure
representativeness of sub-samples.
Measures taken to ensure that the sampling is representative of the in situ
material collected, including for instance results for field duplicate/secondhalf sampling.
Sampling is carried out in accordance with Sandfire protocols as per industry best practice.
No field duplicates have been taken.
Criteria
Quality of assay
data and laboratory
tests
Verification of
sampling and
assaying
Location of data
points
JORC Code Explanation
Commentary
Whether sample sizes are appropriate to the grain size of the material
being sampled.
The sample sizes are considered appropriate for the structurally hosted copper mineralisation
style.
The nature, quality and appropriateness of the assaying and laboratory
procedures used and whether the technique is considered partial or total.
For geophysical tools, spectrometers, handheld XRF instruments, etc, the
parameters used in determining the analysis including instrument make
and model, reading times, calibrations factors applied and their derivation,
etc.
Samples are assayed using Mixed 4 Acid Digest (MAD) 0.3g charge and MAD Hotbox 0.15g
charge methods with ICPOES or ICPMS. The samples are digested and refluxed with a mixture
of acids including Hydrofluoric, Nitric, Hydrochloric and Perchloric acids and conducted for
multi elements including Cu, Pb, Zn, Ag, As, Fe, S, Sb, Bi, Mo, Re, Mn, Co, Cd, Cr, Ni, Se,
Te, Ti, Zr, V, Sn, W and Ba. The MAD Hotbox method is an extended digest method that
approaches a total digest for many elements however some refractory minerals are not
completely attacked. The elements S, Cu, Zn, Co, Fe, Ca, Mg, Mn, Ni, Cr, Ti, K, Na, V are
determined by ICPOES, and Ag, Pb, As, Sb, Bi, Cd, Se, Te, Mo, Re, Zr, Ba, Sn, W are
determined by ICPMS. Samples are analysed for Au, Pd and Pt by firing a 40g of sample with
ICP AES/MS finish. Lower sample weights are employed where samples have very high S
contents. This is a classical FA process and results in total separation of Au, Pt and Pd in the
samples.
The analytical methods are considered appropriate for this mineralisation styles.
No geophysical tools are used in the analysis.
Nature of quality control procedures adopted (eg standards, blanks,
duplicates, external laboratory checks) and whether acceptable levels of
accuracy (i.e. lack of bias) and precision have been established.
Sandfire DeGrussa QAQC protocol is considered industry standard with standard reference
material (SRM) submitted on regular basis with routine samples. SRMs and blanks are inserted
at a minimum of 5% frequency rate.
The verification of significant intersections by either independent or
alternative company personnel.
Significant intersections have been verified by alternative company personnel.
The use of twinned holes.
None of the drillholes in this report is twinned.
Documentation of primary data, data entry procedures, data verification,
data storage (physical and electronic) protocols.
Primary data are captured on field tough book laptops using Logchief™ Software. The software
has validation routines and data is then imported into a secure central database.
Discuss any adjustment to assay data.
The primary data is always kept and is never replaced by adjusted or interpreted data.
Accuracy and quality of surveys used to locate drill holes (collar and
down-hole surveys), trenches, mine workings and other locations used in
Mineral Resource estimation.
Sandfire Survey team undertakes survey works under the guidelines of best industry practice.
All drill collars are accurately surveyed using RTK GPS system within +/-50mm of accuracy
(X,Y,Z).
Downhole survey completed by gyroscopic downhole methods at regular intervals.
Criteria
JORC Code Explanation
Commentary
Specification of the grid system used.
Coordinate and azimuth are reported in MGA 94 Zone 50.
Quality and adequacy of topographic control.
Data spacing for reporting of Exploration Results.
Topographic control was established LiDar laser imagery technology.
Drill spacing is currently defined by geological criteria regarded as appropriate to determine the
extents of mineralisation. This is nominally an 80m by 80m spacing. Spacing is shown by in the
accompanying tables and collar plans. Some holes are drilled at a closer spacing to determine
the edges of mineralisation.
Whether the data spacing and distribution is sufficient to establish the
degree of geological and grade continuity appropriate for the Mineral
Resource and Ore Reserve estimation procedure(s) and classifications
applied.
Whether sample compositing has been applied.
Drilling is preliminary in its spacing and distribution and is not sufficient to at this stage to
support Mineral Resources or Ore Reserves.
No sample compositing have been applied to the Exploration Results.
Whether the orientation of sampling achieves unbiased sampling of
possible structures and the extent to which this is known, considering the
deposit type.
The drillhole may not necessarily be perpendicular to the orientation on the intersected
mineralisation.
If the relationship between the drilling orientation and the orientation of
key mineralised structures is considered to have introduced a sampling
bias, this should be assessed and reported if material.
No significant orientation based sampling bias is known at this time. The drillholes may not
necessarily be perpendicular to the orientation of the intersected mineralisation. Downhole
intervals are converted to estimated true-widths.
Sample security
The measures taken to ensure sample security.
Appropriate security measures are taken to dispatch samples to the laboratory. Chain of custody
of samples is being managed by Sandfire Resources NL. Samples are stored onsite and
transported to laboratory by a licence transport company in sealed bulker bags. The laboratory
receipts received samples against the sample dispatch documents and issues a reconciliation
report for every sample batch.
Audits or reviews
The results of any audits or reviews of sampling techniques and data.
No external audits or reviews of the sampling techniques and data have been completed.
Data spacing and
distribution
Orientation of data
in relation to
geological structure
Share your feedback
Discover