RIU Sydney Resources Round-up Presentation
Released
Released
Announcement PDF
Supplying Global Demand
Presentation
May 2021
Important information
Disclaimer
This document has been prepared by VRX Silica Limited. The information contained in this document is for information purposes only and has been prepared for use in conjunction with a verbal presentation and should be read in that context.
The information contained in this document is not investment or financial product advice and is not intended to be used as the basis for making an investment decision In preparing and providing this document, VRX has not considered the objectives,
investment profile, financial position or needs of any particular recipient Mineral exploration is subject to significant risk T here is no guarantee of exploration success, and even if exploration success is achieved, there is no guarantee that development
of any mineral deposit will be economically viable VRX strongly suggests that investors consult a financial advisor prior to making an investment decision.
No representation or warranty, express or implied, is made as to the fairness, accuracy, completeness or correctness of the information, opinions and conclusions contained in this presentation To the maximum extent permitted by law, none of VRX, its
related bodies corporate, or their shareholders, directors, officers, employees, contractors, agents or advisors, nor any other person accepts any liability, including, without limitation, any liability arising out of fault or negligence for any loss arising from
the use of information contained in this document.
This document may include “forward looking statements” within the meaning of securities laws of applicable jurisdictions Forward looking statements can generally be identified by the use of the words “anticipate“, believe”,“ expect”,“ project”,“
forecast”,“ estimate”,“ likely”,“ intend”,“ should”,“ could”,“ may”,“ target”,“ plan”,“ guideline”,“ and other similar expressions Indications of, and guidance on, revenue models, pricing, earnings and financial position and performance are also forward
looking statements.
Such forward looking statements are not guarantees of future pricing, performance and events, and involve known and unknown risks, uncertainties and other factors, many of which are beyond the control of VRX, its related bodies corporate, and their
directors, officers, employees, contractors, agents and advisors, that may cause actual results to differ materially from those expressed or implied in such statement Actual results, performance or achievements may vary materially from any projections
and forward looking statements and the assumptions on which those statements are based In particular, potential revenue opportunities and guideline pricing models set out in this document are based on certain assumptions which may in time prove
to be false, inaccurate or incorrect Readers are cautioned not to place undue reliance on forward looking statements and VRX assumes no obligation to update such information.
This document is not, and does not constitute, an offer to sell or the solicitation, invitation or recommendation to purchase any securities in any jurisdiction, and neither this presentation nor anything contained in it forms the basis of any contract or
commitment Without limiting the foregoing, this document does not constitute an offer to sell, or a solicitation of an offer to buy, any securities in the United States The securities of VRX have not been, and will not be, registered under the U S Securities
Act of 1933 as amended (Securities Act) or the securities laws of any state or other jurisdiction of the United States, and may not be offered or sold in the United States except in compliance with the registration requirements of the Securities Act and
any other applicable securities laws or pursuant to an exemption from, or in a transaction not subject to, the registration requirements of the Securities Act and any other applicable securities laws.
Competent Persons Statement
The information in this report that relates to Arrowsmith North, Arrowsmith Central and Muchea Exploration Results and Muchea Aircore Drilling Area Mineral Resources are based on data collected and complied under the supervision of Mr David Reid,
who is a full-time employee of VRX Silica. Mr Reid, BSc (Geology), is a registered member of the Australian Institute of Geoscientists and has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and
the activity being undertaken to qualify as a Competent Person under the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code). Mr Reid consents to the inclusion of the data in the
form and context in which it appears.
The information in this report that relates to Arrowsmith North, Arrowsmith Central and Muchea Auger area Mineral Resources is based on information compiled by Mr Grant Louw who is a full-time employee of CSA Global, under the direction and
supervision of Dr Andrew Scogings, who is an Associate of CSA Global. Dr Scogings is a Member of the Australasian Institute of Mining and Metallurgy and a Member of the Australian Institute of Geoscientists. He is a Registered Professional Geologist in
Industrial Minerals. Dr Scogings has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as Competent Person as defined in the 2012 edition of the
Australasian Code for the Reporting of Exploration Results, Mineral Resources, and Ore Reserves (JORC Code). Dr Scogings consents to the disclosure of information in this report in the form and context in which it appears.
The information in this report that relates to Arrowsmith North, Arrowsmith Central and Muchea Probable Ore Reserves is based on data collected and compiled under the supervision of Mr David Reid, who is a full-time employee of VRX Silica. Mr Reid,
BSc (Geology), is a registered member of the Australian Institute of Geoscientists and has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and the activity being undertaken to qualify as a
Competent Person under the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code). Mr Reid consents to the inclusion of the data in the form and context in which it appears.
Investment highlights
Only ASX-listed, pure-play silica sand stock with advanced development assets with 100+ year production life
1. 100% owner of three high value Silica Sand Projects in Western Australia - Tier 1 mining region.
2. Multi-decade-scale contiguous sand deposits with combined 1,056Mt Resource, SiO2 grade 99.6% to 99.9%.
3. Strong interest from potential customers in SE Asia at time of rising global demand imbalance
4. 3-project BFS declared post-tax NPV10 of $728m, capex of just $87m, annual EBIT of $137m and IRR of 83%*
5. Arrowsmith North to lead staggered/disciplined development – first production late 2021
– followed by Muchea and Arrowsmith Central
6. Mining Leases and Miscellaneous Licenses granted; environmental permitting well advanced
7. Scale of VRX projects could prove trigger for long-term opportunity for glass manufacturing industry in
Western Australia.
* See note on page 14
** All currencies Australian dollars unless otherwise indicated
3
Corporate Summary
Capital Structure
Share Price
Ordinary Shares on Issue
508 million
Options on Issue
69 million
Market Capitalisation
Person
Role
Experience
28.5cps *
$145 million*
Cash
$9 million
Debt
Nil
Enterprise Value
$136 million
Paul Boyatzis
Chairman
Governance: Over 30 years experience in investment, equity
markets and managing public companies
Bruce Maluish
Managing
Director
Technical and Finance: Over 35 years in mining industry
including previous roles as ASX MD and General Manager
Board and Management
15.1%
Peter
Pawlowitsch
Director
Finance and Corporate: Mining and software executive
Top 20 Total
29.3%
Steven
Papadopoulos
Commercia
l Manager
Legal and Commercial: Over 20 years experience as corporate
lawyer and commercial advisor in resources and other
industries
Broker Coverage
Yoonil Kim
Marketing
Manager
Marketing: 16 years’ experience selling silica sand in the Asian
market
Shareholders
Argonaut
Euroz Hartleys
* Closing share price on 5 May 2021
4
“Sand is the main material
that modern cities are made of ”
Vince Beiser
“The World in a Grain” 2018
The story of sand and how it
transformed Civilisation
Silica sand
The foundation of modern cities
•
Silica sand is the most-used commodity on the planet after air
and water.
•
It is the main ingredient in all types of glassmaking, including specialty
solar panel and high-tech glass.
•
Silica sand is also the main ingredient in concrete.
•
It is a finite resource that is running out.
•
Around 47% of the world’s glass is made in Asia, and the glass
manufacturing industry is increasing at a rate of 5-6% per year – or
about 8-10 million tonnes.
•
The Asia-Pacific region is currently experiencing a supply shortfall
driving the price up enough to make mining in Australia and shipping to
Asia profitable.
6
Silica sand price and demand dynamics
Silica Sand is forecast to increase in price across Asia-Pacific countries in line with rising demand and supply
constraints due to depletion and environmental restrictions on dredging
Asia Pacific Silica Sand Consumption
Historic and Forecast Silica Sand Pricing
Flat & Container Glass Silica (millions of tonnes)
Flat & Container Glass, Average Price, $US/ tonne FOB
180
50
160
45
140
120
40
100
35
80
60
30
40
25
20
0
20
2016
2017
2018
2019
2020F
Actual
2021F
2022F
Forecast
2023F
2024F
2025F
2016
2017
2018
2019
2020F
Actual
2021F
2022F
2023F
2024F
2025F
Forecast
Source: IMARC Group
7
Demand not met by existing production
Key countries in the Asia Pacific region have unmet demand from local production only
Asia Pacific Silica Sand Market
Silica sand (millions of tonnes)
Largest Net Importers of Silica Sand in Asia Pacific Region
Consumption
Production
Silica (thousands of tonnes)
Import
150
2500
120
2000
90
1500
60
1000
30
500
0
Export
0
2014
2015
2016
2017
2018
2019
China
Taiwan
Japan
Singapore
South Korea
Source: IMARC Group
1. Production aggregated from China, India, Malaysia, South Korea, Japan and Australia
8
Silica Sand – World Class Portfolio
Project development pipeline to ensure disciplined,
staged development of world-class assets
1. Source: VRX Bankable Feasibility Studies
•
100% ownership
•
Three large scale, high grade and low impurity silica sands projects
– Arrowsmith North, Arrowsmith Central and Muchea
•
Each project can be run independently
•
BFSs for all three projects completed late 2019 following:
• Exploration and Mineral Resource Estimation
• Metallurgical testwork
• Process circuit design
• Design engineering
• Capital estimate
•
Simple and environmentally friendly mining process
•
Access to established infrastructure (logistics, power, water)
– rail lines to port run adjacent to all project tenements
•
Granted Mining Leases with secure tenure
•
Permitting well-advanced
9
Arrowsmith North
Arrowsmith North Capex
Near-term development opportunity on a world-class silica sand
project
•
Production forecast to commence in late CY2021
•
25 years’ production with potential for 100+ year minelife
•
223Mt ore reserve @99.7% SiO2
•
~$30m for simple “off the shelf” 2Mtpa processing plant.
•
Access to established infrastructure (rail, port) – rail lines run adjacent to
project tenements
•
Water from Yarragadee North
•
Adjacent to Brand Highway
•
Hybrid gas and solar power supply
Process Plant
Local Infra. Feed bin
Trommel,
pump
Contin.
Total
Capex $28.3m
25 Year EBIT $1,144m (av. $46m/yr)
Source: VRX Bankable Feasibility Studies
10
Arrowsmith North
To date
• Bankable Feasibility
Study complete
• Mining Lease granted
• Miscellaneous Licences
for access granted
• Native Title ILUA in place
• Water licences ready
• Processing plant access
negotiations underway
Arrowsmith North
TIMELINE
Commence
Construction
June 2021
Approvals / Permitting
December 2021
Construction
Commence
Production
December 2022
Next steps 2021
• Finalise offtake
agreements
• Results from completed
grade control drilling
• EPA and mining approval
• MOU Geraldton Port
• MOU rail access
• Financing
• Construction
• First production
Production
Arrowsmith North
11
Muchea
Large scale, high-grade and low impurity silica sand project
•
Construction/Production forecast to commence late 2022
•
99.9% SiO2 - Fe2O3 <100ppm after processing
•
Access to the premium ultra-clear glass market
•
Off-the-shelf mining method and ~$30m plant
•
Access to established infrastructure
• Grid power
• Water from Yaragadee aquifer
• Adjacent to Brand Highway
• Underutilised railway connects to Kwinana (100km)
•
Formal agreement reached with representatives of the Whadjuk People
Native Title Claim Group
•
Granted Mining Lease and Miscellaneous Licences for access
Muchea Capex
Process Local
Plant Infrast.
Feed
bin
Overland Trommel, Ancil. Contin. Total
conveyor pump
equip.
Capex $32.7m
25 Year EBIT $1,540m (av. $62m/yr)
Source: VRX Bankable Feasibility Studies
12
Muchea
Project Timeline
TIMELINE
Commence
Production
Commence
Construction
2021
Approvals/Permitting
2022
Construction
2023
Production
To date
Next steps 2021-23
• Bankable Feasibility
Study complete
• Native Title agreement
in place
• Mining lease granted
• Miscellaneous Licences
for access granted
• Environmental studies
undertaken
• Grade control drilling
POW application
• Finalise and submit EPA
referral
• Secure offtake
agreements
• MOU Kwinana Port
• MOU rail access
• Financing
• Construction
• First production
Muchea
13
Exceptional Project Economics
All three projects have exceptional standalone economics over the first 25 years*
Arrowsmith
North
Arrowsmith
Central
Muchea
$338 M
$242 M
$148 M
$28.3 M
NPV
Capex
IRR 79%
$32.8 M
$25.9 M
NPV
Capex
IRR 60%
NPV
Capex
IRR 83%
*Full details of the bankable feasibility studies for the Arrowsmith North, Arrowsmith Central and Muchea Silica Sand Projects, including material assumptions,
are contained in VRX’s ASX announcements of 28 August 2019, 17 September 2019 and 18 October 2019, respectively. All such material assumptions continue to
apply and have not materially changed. Whilst VRX considers all of the material assumptions to be based on reasonable grounds, there is no certainty that they
will be correct or that the range of outcomes indicated within the studies will be achieved.
14
Processing Flowsheet identical
across all three projects
Simple processing, no chemicals and no dust, 2mtpa processing plant at each site
Processing Plant Design
Loader Feeder
Trommel Screening
Attritioning Cells
Classifier
▪
Stockpiles
Wednesday, 5 May 2021
Product Drying
Size
Screening
Magnetic
Separation
Spiral
Separation
▪
Arrowsmith North,
Arrowsmith Central and
Muchea to each have 2 Mtpa
processing capacity
No chemicals required
15
Responsible Mining – The VRX Way
A made-for-purpose mining method designed
around instant rehabilitation
•
VRX has developed a unique and progressive mining
method for its silica sand projects
•
The Vegetation Direct Transfer (VDT) method lends
itself to rapid and extensive regeneration of affected
areas based on continuous rehabilitation as silica sand
mining progresses
•
Root structures in the loose sand are relatively shallow
at 200-300mm in depth.
•
The VDT method removes a 400mm-deep sod with
topsoil containing the vast majority of native flora and
invertebrate fauna remining intact
•
See a video demonstration here
16
Sustainability
Environmental, Social and Governance (ESG)
VRX is delivering on its ESG responsibilities aligned to the UN’s Sustainable Development Goals
CLEAN ENERGY
Utilising reliable,
renewable
modern energy
ECONOMIC
GROWTH
INDUSTRY
INNOVATION
SUSTAINABLE
COMMUNITIES
RESPONSIBLE
PRODUCTION
CLIMATE
ACTION
REHABILITATION
PLAN
Enhancing
economic and
productive
employment
Building
resilient
infrastructure
and fostering
innovation
Respecting
heritage values
Employing
sustainable
mining
methods
Reducing
emissions from
production
Employing direct
vegetation
transfer as
a unique
rehabilitation
method
17
The right place to mine and
the right time to invest
1. Access to very long life, high-grade 100% owned silica sand supply
2. Access to the lucrative high-tech ultra clear glass market
3. No restrictions on export from a low sovereign risk country
4. Strong offtake interest from potential South East Asia at a time of global supply imbalance
5. Strong project economics with low start up Capex
6. Long life Mining Leases, subject to final environmental permitting processes
7. Opportunity to build a glass manufacturing industry in Western Australia
18
Thank you
Bruce Maluish
Managing Director
Level 1, 6 Thelma Street
West Perth WA 6005
Phone: 08 9226 3780
Email: brucem@vrxsilica.com.au
Share your feedback
Discover